Posted by RRKen on Sunday, October 31, 2010 8:07 PM

schlimm
In point of fact, Barrington Hills is the section of the Barrington area that has most of the "horsey set"  with estates that in many cases include stables.  However, if you actually read my words, you will see that I never said Barrington was not affluent.  I included benburch's term "better-off" in quotes, because Barrington Hills is even wealthier than Barrington. 

All of that is really quite irrelevant to the real points that ICLand and I (and possibly other posters), which you and others are unable or unwilling to address.

In point of fact, they are mostly snobs up there from my experience.  Allow me to qualify that after 35 years living on the South Side, it was also considered a foreign country as was everthing north of I-55!

I never drink water. I'm afraid it will become habit-forming.
W. C. Fields
I never met a Moderator I liked
  • Member since
    August 2004
  • From: The 17th hole at TPC
  • 2,283 posts
Posted by n012944 on Sunday, October 31, 2010 8:13 PM

schlimm

3.  The UP line was also blocked.  If the CN had blocked the UP in West Chicago on that extremely busy freight mainline, I wonder if the anti-NIMBY complaints would be different?

3.  Regardless, the idea of just doing whatever you want on your property is highly irresponsible.  Railroads should strive to be good citizens in the communities they pass through.  Most do.  For example, the people of Barrington do not complain about the UP ex-C&NW line, used by Metra commuter trains.  Perhaps CN is a bad apple?

3.  Why would the complaints be different?  Knuckles happend, some across diamonds, some across road crossings, anyone who knows anything about railroads know that.  I had a QNPSKP train get a knuckle across 75th street a while back.  It had both the BRC and Metra Southwest x Wabash line blocked, along with some local road crossings.  There where no local articles in the Trib, no complaining from the locals.  Maybe the locals in and around 75th are not the same NIMBYS that exist in Barrington, or maybe since the locals don't have the $$$ that Barrington locals have the Trib didn't care....

 

3. The people of Barrington complained to Metra when it looked at the circle route over the J a while back.......Perhaps CN is not a bad apple but the people of Barrington are?

An "expensive model collector"

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Sunday, October 31, 2010 9:25 PM

n012944
Perhaps CN is not a bad apple but the people of Barrington are?

The petty Bourgeoisie of Barrington...

 

 

  • Member since
    May 2010
  • 172 posts
Posted by ICLand on Monday, November 1, 2010 8:33 AM

ICLand

Generally, a break in a train is part of the contingency planning that all Class I railroads develop and review from time to time -- pre-arranged response protocols to breaks, derailments, hazmat, earthquakes, etc..  Ordinarily, a break at a crossing is treated as an "incident" and there is a plan for it, to get the train separated at the crossing as soon as practicable. This is so that 1) local public relations doesn't go down the outhouse drain, and 2) emergency vehicles are not delayed or prevented from responding. All the railroad company needs is for some little kid to bleed to death or the mayor die of a heart attack because the ambulance couldn't arrive in time because of a blocked crossing. And then you've got headlines, legislators, Congressmen, and lawsuits all thrown into a very expensive mix.

CN is a railroad company I have no experience with. But, on American Class I's, the length of time that this crossing was tied up suggests about a 99.9% probability that someone got called on the carpet for it.

The "incident plan" for this kind of event failed, miserably, for some reason. And while it may be a 1 in a million event, every such event is a measure of the company's ability to implement it's incident plans.

And something clearly fell apart here. And railroad people don't just wander around in a fog, dealing with unplanned breaks, and offering lame "oh gee, it only happens once in a great while," excuses. No, these are professionals, and as soon as the break was reported, "someone" was responsible for identifying the crossings involved, bringing up power from the next train on line, breaking the train ahead of the crossing, and pulling it back 40 feet to clear the crossing. Repeat if more than one. Reverse the process if the original break or derailment is at the rear of the train, which was unlikely.

Consider the ability to do this quickly a "test."  CN failed on this one. Of course people were angry. So was the CN Vice President of Operations, I would bet. He knows exactly what that failure meant: young dispatcher who didn't get the memo, trainmaster who off at the races, train crew distracted by their event. Who knows? But the crossing was blocked for a very long time and regardless of the railroad company, there was a plan in place to avoid that, and it failed.

Here's what the railroad knows: this was their protocol performance with a relatively innocuous event. Doesn't happen very often.

Neither does a Hazmat spill.

The company knows that there are events that occur when those crossings need to be open so that the railroad company and first responders can get to the disaster and, among other things, save the train crew, and likely evacuate the area.

Hard to do with a railroad-caused traffic jam.

This is one of those incidents that brings down a lot of Monday-morning quarterbacking at the professional level because they know just how serious the consequences can be.  Sure people got angry. But a railroad's professional staff knows more clearly and realistically why people should have been angry. Call it what they know it could have been: a close call.

  • Member since
    September 2009
  • 48 posts
Posted by HTower on Monday, November 1, 2010 9:12 AM

You can't have it both ways. 

As you said, the UP line through Barrington is mostly passenger Metra.  There's very little freight traffic on the line.  Next you state that Barrington doesn't complain about the UP line.  "Duh" comes to mind.  Residents of Barrington aren't going to complain about a low traffic line that is mostly passenger and serves them directly.  They would certainly start squawking if UP started running 15 intermodal trains each way everday. 

 

CN is very much at fault for the breakdown, I haven't seen anyone say otherwise.  Breakdowns do happen though, as much as everyone wishes they didn't, they still do.    If the breakdown happened while crossing the UP West Line it would still have been an accident, and a regrettable one as well nothing malicious about it.  The dispatchers in Omaha would most likely have to work extra hard to prevent trains from stacking up in queue all the way from West Chicago to LA

  • Member since
    November 2004
  • From: Elgin, IL
  • 84 posts
Posted by benburch on Monday, November 1, 2010 9:53 AM

Whose car was it that had the knuckle break?  I think that CN can hardly be responsible if some foreign car had a knuckle break, for example.   And even if it was their car, no reasonable inspection can catch all of the defects that can cause this.  This is just one of those things that happen like flat tires.

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Monday, November 1, 2010 10:12 AM

This thread seems to have divided into two opposing viewpoints:

 

1)      CN is negligent for causing an unreasonable delay.

2)      Break-in-twos are normal, unpredictable, and can happen anywhere, and Barrington residents or others who complain about delay are NIMBYS, morons and idiots that have no basis for a complaint, and should realize that railroads have a perfect right to delay everybody else for as long as they want to.

 

I adhere to item #1.  However, it is not clear to me which side RR Ken and Murray are on.  By giving an “Amen” to IC Land, I assume they support viewpoint #1.   

  • Member since
    September 2009
  • 48 posts
Posted by HTower on Monday, November 1, 2010 10:31 AM

Wow.

  • Member since
    November 2004
  • From: Elgin, IL
  • 84 posts
Posted by benburch on Monday, November 1, 2010 1:45 PM

Bucyrus
This thread seems to have divided into two opposing viewpoints:
 
1)      CN is negligent for causing an unreasonable delay.
2)      Break-in-twos are normal, unpredictable, and can happen anywhere, and Barrington residents or others who complain about delay are NIMBYS, morons and idiots that have no basis for a complaint, and should realize that railroads have a perfect right to delay everybody else for as long as they want to.
 

I adhere to item #1.  However, it is not clear to me which side RR Ken and Murray are on.  By giving an “Amen” to IC Land, I assume they support viewpoint #1.   

OK, then, you are in possession of knowledge that railroad companies would pay you millions for! 

How can you prevent or predict knuckle failure?

  • Member since
    May 2010
  • 172 posts
Posted by ICLand on Monday, November 1, 2010 3:53 PM

benburch

OK, then, you are in possession of knowledge that railroad companies would pay you millions for! 

How can you prevent or predict knuckle failure?

Aside from the fact that I suspect you've never "carried a knuckle" in your life, I don't think you understand the point that is being discussed between the various gentlemen. The dispute appears to me not to be over whether or not a knuckle failed, but the railroad company's response to it, which resulted in a lengthy delay, apparently at a critical crossing, causing a substantial traffic tie-up. 

If there were more to story, and it were being told by a knowledgeable observer, I would suspect that not only did the company drop the ball on clearing the crossings according to their own pre-arranged contingency plan, but that the truck carrying the replacement knuckle was held up in the traffic caused by not clearing the crossings in a timely fashion. This is called "shooting yourself in the foot."

But, again, I wasn't there, and the story may be richly laden with ironies, or maybe not but I am sure the whole picture was not reported. However, confusing cause -- knuckle -- with effect -- massive traffic tie-ups -- confuses the issues for reasons I cannot discern. One is not the other.

  • Member since
    November 2004
  • From: Elgin, IL
  • 84 posts
Posted by benburch on Monday, November 1, 2010 4:49 PM

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

And what I do not see is any discussion of why it took time to fix.  I've deal with a lot of broken machinery and sometimes you find a routine repair that takes a whole lot longer than it ought to because something is bent, broken, or stuck.  Requiring a tool you do not have.

How long do you think it ought to take to fix a broken knuckle? Is there some guidance as to the standard amount of time?

And was there an issue with the spare knuckles on the locomotive?  Did they have the usual compliment of knuckles or were they short?

And if indeed a service truck had to come down from Mundeline with a coupler, why does anybody expect that it would not have been caught in traffic if the train created a traffic jam?  Are they supposed to bend the laws of physics and fly there?

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Monday, November 1, 2010 5:21 PM

benburch

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

And what I do not see is any discussion of why it took time to fix. 

How long do you think it ought to take to fix a broken knuckle?

 

I have not heard anyone say that knuckles should never break.  And, as has been mentioned several times in this thread, the issue has nothing to do with how much time it should take to fix a broken knuckle.  The issue is why the CN did not cut the crossing during the repair.

  • Member since
    January 2006
  • From: Northeast OH
  • 2,268 posts
Posted by NeO6874 on Monday, November 1, 2010 5:41 PM

benburch

... Are they supposed to bend the laws of physics and fly there?

 

well, they could've taken a train Smile, Wink & Grin.

 

Yeah, moving the train ahead could have helped clear some (all?) of the crossings, though could it have cleared SR 14?  Maybe I missed it, but I didn't see any indication that moving the still-operational half of the train *would* have cleared that one crossing (or that they *didn't* move some or all of the train out of the way).  I don't disagree that not clearing out the crossings that they *could have* was a bad idea (tm).

To the professional railroader types --> IF they could have closed the open trainline at the "new" end of the train, it would have taken about 10 minutes (or thereabouts) to get back up to operating pressure, plus whatever time is necessary to do a brake test (presumably there's *something* that has to be done after they go into emergency) right?

for the sake of argument, let's say they did that, AND had a knuckle dropped off at the head end.  so, we're at about 20-30 minutes since emergency.  So far, the conductor has gotten to the break, and checked it out; gotten air pressure back into the trainline, done a brake test if necessary.

Ride up to the knuckle, pick it up, and go back. another few minutes (5-10). 

so, now we've had this break for nearly 3/4 of an hour before the conductor can even start working on the bad knuckle.  45 minutes or so to get the old one out, and the new one in, brake test, and continue onward seems *VERY* good to me (note I'm not a pro railroader... just volunteer with a historical group on weekends... so my times may be significantly skewed...)

 

-Dan

Builder of Bowser steam! Railimages Site

  • Member since
    May 2003
  • From: US
  • 25,292 posts
Posted by BaltACD on Monday, November 1, 2010 5:43 PM

It is exceedingly difficult to cut crossings that are blocked by cars on the porition of the train that has no locomotive attached to it and the movable portion of the train is prevented from coupling to the unmovable portion of the train by a broken knuckle. Duh!

Bucyrus

 benburch:

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

And what I do not see is any discussion of why it took time to fix. 

How long do you think it ought to take to fix a broken knuckle?

 

 

I have not heard anyone say that knuckles should never break.  And, as has been mentioned several times in this thread, the issue has nothing to do with how much time it should take to fix a broken knuckle.  The issue is why the CN did not cut the crossing during the repair.

Never too old to have a happy childhood!

              

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Monday, November 1, 2010 6:01 PM

BaltACD

It is exceedingly difficult to cut crossings that are blocked by cars on the porition of the train that has no locomotive attached to it and the movable portion of the train is prevented from coupling to the unmovable portion of the train by a broken knuckle. Duh!

 Bucyrus:

 benburch:

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

And what I do not see is any discussion of why it took time to fix. 

How long do you think it ought to take to fix a broken knuckle?

 

 

I have not heard anyone say that knuckles should never break.  And, as has been mentioned several times in this thread, the issue has nothing to do with how much time it should take to fix a broken knuckle.  The issue is why the CN did not cut the crossing during the repair.

 

Yes, I fully understand that you can't cut the crossing with the lead locomotive if the knuckle is broken.  I am assuming that CN has more than one locomotive though.  Do you have information that there was no possiblity of cutting the crossing because no other locomotive was available to pull the hind end back?  If not, why would you assume that?  It seems relatively improbable.

  • Member since
    August 2004
  • From: The 17th hole at TPC
  • 2,283 posts
Posted by n012944 on Monday, November 1, 2010 6:53 PM

Bucyrus

 BaltACD:

It is exceedingly difficult to cut crossings that are blocked by cars on the porition of the train that has no locomotive attached to it and the movable portion of the train is prevented from coupling to the unmovable portion of the train by a broken knuckle. Duh!

 Bucyrus:

 benburch:

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

And what I do not see is any discussion of why it took time to fix. 

How long do you think it ought to take to fix a broken knuckle?

 

 

I have not heard anyone say that knuckles should never break.  And, as has been mentioned several times in this thread, the issue has nothing to do with how much time it should take to fix a broken knuckle.  The issue is why the CN did not cut the crossing during the repair.

 

 

Yes, I fully understand that you can't cut the crossing with the lead locomotive if the knuckle is broken.  I am assuming that CN has more than one locomotive though.  Do you have information that there was no possiblity of cutting the crossing because no other locomotive was available to pull the hind end back?  If not, why would you assume that?  It seems relatively improbable.

Do you information that there was?  How about a crew to use it?  Most railroads unions require a 2 hour call for a new crew to come out.  According to the report this whole thing took between 90 minutes and 2 hours to replace the knuckle.  Even if there was an engine RIGHT BEHIND THE TRAIN, it still wouldn't have helped clear the crossings any quicker.  I doubt that there was a crew sitting around on a set of power doing nothing, the CN isn't known for having crews being on duty and not working.  Any crew would have to tied down its train and travel to the area, which could take anywhere from 45 minutes to 2 hours.  Was there a crew in the area?  Or are you just assuming that there was?

An "expensive model collector"

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Monday, November 1, 2010 8:11 PM

n012944

 Bucyrus:

 BaltACD:

It is exceedingly difficult to cut crossings that are blocked by cars on the porition of the train that has no locomotive attached to it and the movable portion of the train is prevented from coupling to the unmovable portion of the train by a broken knuckle. Duh!

 Bucyrus:

 benburch:

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

And what I do not see is any discussion of why it took time to fix. 

How long do you think it ought to take to fix a broken knuckle?

 

 

I have not heard anyone say that knuckles should never break.  And, as has been mentioned several times in this thread, the issue has nothing to do with how much time it should take to fix a broken knuckle.  The issue is why the CN did not cut the crossing during the repair.

 

 

Yes, I fully understand that you can't cut the crossing with the lead locomotive if the knuckle is broken.  I am assuming that CN has more than one locomotive though.  Do you have information that there was no possiblity of cutting the crossing because no other locomotive was available to pull the hind end back?  If not, why would you assume that?  It seems relatively improbable.

 

Do you information that there was?  How about a crew to use it?  Most railroads unions require a 2 hour call for a new crew to come out.  According to the report this whole thing took between 90 minutes and 2 hours to replace the knuckle.  Even if there was an engine RIGHT BEHIND THE TRAIN, it still wouldn't have helped clear the crossings any quicker.  I doubt that there was a crew sitting around on a set of power doing nothing, the CN isn't known for having crews being on duty and not working.  Any crew would have to tied down its train and travel to the area, which could take anywhere from 45 minutes to 2 hours.  Was there a crew in the area?  Or are you just assuming that there was?

I cannot rule out the possibility that cutting the crossing was completely beyond the capability of the CN.

  • Member since
    May 2010
  • 172 posts
Posted by ICLand on Monday, November 1, 2010 9:38 PM

benburch

No, I get that they think the delay was excessive, what I don't get is that they seem to think that this never should have happened at all.

I haven't read that on this thread. You seem to want to create an argument where none exists.

It takes about 5 minutes to drop a broken knuckle. Move the train up to where the engineer has set out a good one, move the train back. If its only five or ten cars back, this whole process can take 15-20 minutes. If there's no spare up front (I've never seen that), I've heard of the next train dropping one off (double track) right at the break. In urban areas, somebody sends out a truck. Whatever is fastest. Time is money. Spare knuckles are pretty much all over the place. It's a railroad. This event is neither news nor unique. Just the time for repair in this instance makes it unusual.

I'm gathering that this train didn't have a spare. Well, yeah, if so, that's a problem all right. There's a reason they always carry a spare. The only other thing that might have held this up was that the knuckle broke far back in the train. That's unusual. CN has had knuckles show up manufactured by Siderúrgica Nacional (Sidena) of Mexico which were woefully prone to breakage. They shouldn't have been in the system.  They haven't been manufactured in years.

However, this was supposed to be "congested" railroading. That seems to be the emphatic point of many posters. If so, then a following train should have been able to provide power to the rear of the train in short order and, assuming the broken knuckle is up front, separate the crossings. That's the usual plan. And no, you don't have to call up a crew for that.

 

  • Member since
    September 2009
  • 48 posts
Posted by HTower on Monday, November 1, 2010 9:51 PM

Where does the article say that the crew didn't have a spare?  No actual information on how the repair was affected was included in the article.

  • Member since
    July 2006
  • 9,610 posts
Posted by schlimm on Monday, November 1, 2010 10:15 PM

This thread demonstrates the problems of speculation when limited factual information is available, or ignoring it even when it is, in some cases.  If you look at the satellite view, you can see the single-tracked CN (as it mostly is along its length) crossing the double-tracked UP.  There is a siding/interchange track on the CN starting about a mile to the west of the diamonds.  Nothing to the east.

BTW: The J early on had overpasses of a number of highways well south of Barrington: Rt. 64, Rt. 38, Rt. 56, to name some.

C&NW, CA&E, MILW, CGW and IC fan

  • Member since
    March 2002
  • 9,265 posts
Posted by edblysard on Tuesday, November 2, 2010 12:35 AM

For arguments sake it seems a few folks have assumed the break apart was in a location that allowed the front part of the train to pull forward enough to clear the crossing under discussion.

Say your facing north on the street, the front of the train is pointed east or moving from your left to right...now lets say the break was on the west or left side of the crossing, then yes, clearing the crossing would be a matter of the conductor walking back, closing the inglenook, pumping the air up, and having the engineer pull ahead enough to clear, you wouldn't even need a brake test considering the situation.

But what if the pull apart was on the right or east side of the crossing?

Pulling ahead would solve nothing.

And we have no real knowledge of what really broke.

Was it a knuckle, or did the coupler fail?

If it was a knuckle, then the swap out would be pretty much as described as above, have the hogger toss off the right knuckle, drag yourself up to that point, throw the knuckle on the rear crossover platform and shove back to the break, drop the old broken knuckle out and replace, about a 30 to 45 minute job...but if it was a coupler that failed, then nothing the train crew could do in repairs.

So now we are at the "have another locomotive couple into the rear of the train and drag it back" part...well, most railroads don't have locomotives just sitting around, crewed and ready to spring into action.

If they were to have another locomotive cut away from their train, and come up against the rear of the broken train, then that crew would first have to tie down their train, assuming it was in a position and location to safely do so, then travel whatever distance required to reach the rear of the disabled train, couple into it and pump up the air...all of this would have to be considered after the reason for the break apart was determined, and then set in motion, so your looking at best case time wise, 30 to 45 minutes for a broken knuckle, one to two hours for a following locomotive to arrive, couple up, pump up the brakes and move the rear, and that's assuming there was another light locomotive or a train that close.

Everyone is making assumptions about the ability to move the "broken" part of the train when in fact we don't know if the break occurred in a location that allowed a repair truck to gain easy access, if there even was another locomotive in position to move the broken section, or even if there was any locomotive within 30 (10, 15) minutes of access to the rear.

Add in the discovery time of the conductor walking back, finding the break, deciding it was something he or she could not repair, calling in the info and awaiting a decision, then any locomotive coupling up and moving the rear of the train, your looking an hour minimum from the emergency brake application, and that's assuming there were no other issues.

Since everyone is assuming things, lets play this one out.

Train is moving west to east, the break apart happens on the east or "wrong" side of the crossing, so moving the front of the train is useless, and assume the coupler failed, (broken keeper key or the drawbar pin failed, maybe the drawbar itself broke)...lets further the fun by having the rear of the train fouling the only switch that allows easy and quick access to the rear, so the only way a locomotive can get to the rear is to have one dispatched from a yard 10 miles away, (5 mile, 2 miles, pick your poison) and the dispatcher instructs the following locomotive to assist the lead train, which will require by rule the following locomotive to proceed at restricted speed, and require stopping and flagging through the last signal behind the disabled train.

The clock keeps ticking.

So, again, I ask you folks who seem to think it is something that should have been handled quicker how you would go about clearing the crossing faster than what was done?

Lets flip the other way some and assume it is simply a broken knuckle.

Lets say it was on the wrong side of the crossing again, (it wont matter much in this scenario).

I am the conductor, and here is what I would do.

First, we call the dispatcher to let them know we went into emergency braking application, so he can stop following traffic and opposing traffic.

Then we call the trainmaster on duty to inform him what has happened so far.

I tell him I am headed back to the rear to find out what has happened, (remember all we know right now is the train went into emergency, not why it has done so) and he agrees with me the best course of action is to find out what is wrong before we do anything else.

Lets say I have to walk 60 cars back, and find my broken knuckle on the wrong side of the crossing, say 3 or 4 cars past.

I determine it is a E class knuckle, call my engineer to toss a E knuckle off on his side with a lit fusee stuck in it so I can see where it is easier, while he is doing that, I have closed the anglecock, and the train line is pumping up.

During this time, I look as far back towards the rear as best I can on both sides to see if anything looks like it is on the ground, again, so far all we know is a knuckle is broken, not why, it might be the weak link in the chain of a derailment farther back, and this is where the forces involved decided to break the train.

Engineer calls, says his air looks good, so I have him drag me up to the knuckle, I toss it and the spare knuckle pin on the rear crossover platform, we shove back to the break.

I install the new knuckle and pin, couple up the train, cut the air in and once the engineer confirms he has good pressure, and the EOT says the rear car has pressure, letting us know there is a good train line through out the whole train, I have him slowly pull on the train.

It will only take about a car length, if that, for him to decide if the train is acting and moving as easy as it did before.

If so, then I will have him slowly pull the train past the crossing while I stand there and inspect it on this side.

Problem for the crossing solved, and I walk back up the far side to inspect the rest of the train.

If on the other hand, it doesn't move as easily as it did before, or my engineer is not comfortable with moving the train, or we go right back into emergency, I would walk far enough towards the rear to make a cut clear of the crossing circuit, then have him drag the "good" part of the train past the crossing, call the TM and tell him the bad new...crossing problem solved.

Now, you guys figure out how fast any of that that can be done.

By the way, because they didn't simply pull the front part of the train past the crossing tells me that the break apart happened on the "wrong" side to do that...I know of no conductor who wouldn't simply close up the train line and move the part they could if the break was on the good side.

23 17 46 11

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Tuesday, November 2, 2010 8:21 AM

The duration of delay and the inconvenience it caused begs the question of why it was allowed to happen.    The assumptions began with the very premise of the thread title.  That is that the complainers were NIMBYS who could not tolerate a little inconvenience that the CN had every right to cause, and no way to prevent.  The assumptions have been that the CN could not have been negligent because long crossing blockages can conceivably be unavoidable.  Maybe that was the case, but it is an assumption.

 

So those assumptions in defense of CN gives birth to the devil’s advocate role of assuming that CN was negligent for causing a delay that they could have prevented.  So there are two opposing positions to this thread, and both are based on assumption.  Based on the limited information available about the cause of the delay, it you take away all possible assumptions, the entire thread is moot.  It has no foundation whatsoever. 

  • Member since
    March 2016
  • From: Burbank IL (near Clearing)
  • 13,540 posts
Posted by CSSHEGEWISCH on Tuesday, November 2, 2010 8:23 AM

I would venture to think that the break-in-two on CN and how it was handled is actually a straw man for other issues related to rampant NIMBYism and flight from urban issues.  Barrington and Frankfort both opposed CN's purchase of EJ&E because it represented an intrusion of the outside world on their exclusive pastoral Eden where everything is "just so" and outsiders can be kept at bay.  This is the same mentality that also opposes the widening of arterial roads from two to four lanes even though they are hopelessly congested or opposes installing sidewalks on side streets because the neighborhood will lose that "country" atmosphere, whatever that is.

The daily commute is part of everyday life but I get two rides a day out of it. Paul
  • Member since
    August 2004
  • From: The 17th hole at TPC
  • 2,283 posts
Posted by n012944 on Tuesday, November 2, 2010 10:53 AM

ICLand

However, this was supposed to be "congested" railroading. That seems to be the emphatic point of many posters. If so, then a following train should have been able to provide power to the rear of the train in short order and, assuming the broken knuckle is up front, separate the crossings. That's the usual plan. And no, you don't have to call up a crew for that.

 

 

What following crew?  From what I understand the CN is only running about 10 trains each way a day over the J in Barrington.  Chances are the next train was more than 2 hours behind.

 

BTW what is this so called plan you keep speaking of?  As a dispatcher for a class one railroad I am very interested in it.  We have no set "plan" for a knuckle break, because each break is different. 

An "expensive model collector"

  • Member since
    May 2003
  • From: US
  • 25,292 posts
Posted by BaltACD on Tuesday, November 2, 2010 11:23 AM

I am certainly glad I am invested in a railroad that is operated by railroaders as opposed to the non-railroaders opinions voiced in this thread.

Denial of reality is a terrible thing to lose.

Never too old to have a happy childhood!

              

  • Member since
    May 2010
  • 172 posts
Posted by ICLand on Tuesday, November 2, 2010 11:49 AM

n012944

What following crew?  From what I understand the CN is only running about 10 trains each way a day over the J in Barrington.  Chances are the next train was more than 2 hours behind.

Well, that does change the perspective from the horribly congested, heavy traffic version presented earlier and why Barrington is constantly complaining. I couldn't tell from the "diversity' of opinions whether this was high density Chicago area railroading or low density Rock Island type railroading out in Colorado.Now I see that the railroading is practically "leisurely."

Under similar circumstances (10 trains a day) I do recall a switcher from a yard ten miles away arriving in about 20 minutes to pull the train off the blocked crossing due to a grade crossing collision at the next crossing. And yes, we had a plan for that: it was called "figuring out how to keep the crossings clear" and the written instructions went all the way from where to stop for a meet on ordinary movements, to what to do when crossings were blocked by other than normal train movements:  derailments, grade crossing incidents, hazmat, etc.. This was part of a formal Safety Plan.

Since 2002, these are required as a matter of law for railroads involved in any merger proceeding  by 49 CFR 244.13 as part of Safety Integration Planning. And that rule simply requires that merging railroads standardize individual road Safety Plans, and these plans must specifically (and have for the past 40 years that I am aware of) cover railroad responses to blocked crossings.

"(i) Highway-rail grade crossing systems. Each applicant shall identify a program, including its development and implementation, covering the following: (1) Identification of the highway-rail grade crossings at which there will be an increase in rail traffic resulting from the transaction; (2) An applicant's existing grade-crossing programs as they apply to grade crossings identified in paragraph (i)(1) of this section; (3) Integration of the grade crossing programs of the railroads subject to the transaction to the extent the programs may be different; (4) Emergency response actions; (5) Avoidance of blocked or obstructed highway-rail crossing systems by trains, locomotives, railroad cars, or other pieces of rolling equipment; and (6) Signs employed for changes in rail traffic patterns."


  • Member since
    May 2010
  • 172 posts
Posted by ICLand on Tuesday, November 2, 2010 11:52 AM

n012944
lan you keep speaking of?  As a dispatcher for a class one railroad I am very interested in it.  We have no set "plan" for a knuckle break, because each break is different. 

Didn't say there was a "knuckle" plan.

  • Member since
    August 2005
  • From: At the Crossroads of the West
  • 11,013 posts
Posted by Deggesty on Tuesday, November 2, 2010 12:26 PM

BaltACD

I am certainly glad I am invested in a railroad that is operated by railroaders as opposed to the non-railroaders opinions voiced in this thread.

Denial of reality is a terrible thing to lose.

Well said. Thumbs Up

Johnny

  • Member since
    May 2005
  • From: S.E. South Dakota
  • 13,569 posts
Posted by Murphy Siding on Tuesday, November 2, 2010 3:16 PM

ICLand

Under similar circumstances (10 trains a day) I do recall a switcher from a yard ten miles away arriving in about 20 minutes to pull the train off the blocked crossing due to a grade crossing collision at the next crossing.

  Was that a modern day  occurence,  or back before railroads rationalized manpower and equipment to stay lean and competitive?

Thanks to Chris / CopCarSS for my avatar.

  • Member since
    May 2005
  • From: S.E. South Dakota
  • 13,569 posts
Dumby question.
Posted by Murphy Siding on Tuesday, November 2, 2010 3:29 PM

     What's the difference between a coupler and a nuckle?

Thanks to Chris / CopCarSS for my avatar.

Join our Community!

Our community is FREE to join. To participate you must either login or register for an account.

Search the Community

Newsletter Sign-Up

By signing up you may also receive occasional reader surveys and special offers from Trains magazine.Please view our privacy policy