Posted by zkr123 on Thursday, July 17, 2014 8:59 PM
Why has UP/BNSF purchased SD70AH locomotives? Doesn't a heavier locomotive mean higher fuel consumption? Seems like it is going to cost more to run but I hope I'm wrong.
  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Friday, July 18, 2014 9:16 AM

Heavier locomotives move more tonnage, pretty simple. In the weight range that we're talking with these units the fuel consumption isn't even worth mentioning as is barely affected in the slightest.

ML

  • Member since
    December 2001
  • From: NW Wisconsin
  • 3,857 posts
Posted by beaulieu on Friday, July 18, 2014 10:14 AM

Heavier locomotive means more pulling power. Modern freight locomotives produce enough torque in their electric motors to spin their wheels without moving unless they are heavy. Normal SD70ACe locomotives had a reputation for being a bit slippery, especially in wet weather. The Heavy version does not have that problem.

  • Member since
    May 2013
  • 3,231 posts
Posted by NorthWest on Friday, July 18, 2014 10:43 AM

AC locomotives are limited by their adhesion, their ability to grip the rail. Adding weight increases the adhesion.

  • Member since
    September 2013
  • 2,505 posts
Posted by caldreamer on Friday, July 18, 2014 11:43 AM

So adding few tons to a locomotive in the form of a big block of concrete adds what to the tractive effort and at what cost?  Is the small amount of additional tractive effort worth the cost of a few  tons of concrete?

  • Member since
    August 2004
  • From: The 17th hole at TPC
  • 2,283 posts
Posted by n012944 on Friday, July 18, 2014 11:56 AM

caldreamer

So adding few tons to a locomotive in the form of a big block of concrete adds what to the tractive effort and at what cost?  Is the small amount of additional tractive effort worth the cost of a few  tons of concrete?

caldreamer

So adding few tons to a locomotive in the form of a big block of concrete adds what to the tractive effort and at what cost?  Is the small amount of additional tractive effort worth the cost of a few  tons of concrete?

A few tons of concrete costs almost nothing when compared to the 2 million plus cost of a new locomotive.   If we are talking about the amount of extra fuel needed to move the extra couple of tons look at it this way.  A coal train weights in around 18000 tons, do you think a few extra tons is really going to make a difference?  

An "expensive model collector"

  • Member since
    November 2003
  • From: Rhode Island
  • 2,289 posts
Posted by carnej1 on Friday, July 18, 2014 12:05 PM

caldreamer

So adding few tons to a locomotive in the form of a big block of concrete adds what to the tractive effort and at what cost?  Is the small amount of additional tractive effort worth the cost of a few  tons of concrete?

Yes.

 CSX has been doing this with a large portion of their AC fleet for the last decade or so. They have done a great deal of testing and found that the increased tractive effort offers some significant  improvements in train performance, particularly in coal drag service in mountainous territory.

"I Often Dream of Trains"-From the Album of the Same Name by Robyn Hitchcock

  • Member since
    January 2001
  • From: Atlanta
  • 11,971 posts
Posted by oltmannd on Friday, July 18, 2014 12:13 PM

NorthWest

AC locomotives are limited by their adhesion, their ability to grip the rail. Adding weight increases the adhesion.

You have the right idea, just some clarification on terms.

Adhesion is how well the wheel "sticks" to the rail.  It's expressed as the ratio of tractive force/locomotive weight - usually as a %.  An AC locomotive might have 35% adhesion.  How much tractive force (tractive effort) it can generate depends on it's weight.  The heavier, the harder it can pull.

-Don (Random stuff, mostly about trains - what else? http://blerfblog.blogspot.com/

  • Member since
    September 2003
  • 21,669 posts
Posted by Overmod on Friday, July 18, 2014 1:38 PM

To add a bit more:  Compare the added weight to the overall mass of a loaded train; the additional fuel burn could be measured with sensitive equipment, but is substantially exceeded by the money advantages of being able to use more of the 'available' power of the AC traction motors, and perhaps by the real-world reduction in slipping/microslipping provided by better adhesion.

  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Friday, July 18, 2014 8:30 PM

CSX has essentially standardised on 432,000lbs as the weight of their modern road power since the AC4400s (#475 iirc and full scale orders of heavy CW44AHs starting with the 500s) and NS has also since been buying it's ES44ACs and SD70ACes at the same 432klbs weight. In this case also the weight is not concrete as it doesn't have as much density as steel does, with the new built locomotives the weight is added in the form of thicker frame steel and other bits and pieces, in the case of the CSX AC44s that got weight added it was added in the form of extra steel welded into whatever space they could find. CSX also ballasted up it's SD70MACs (seen by a raised walkway along the right hand side and plates added along the face of the left hand side walkway) before it also got heavy SD70MAC-T1s.

It's quite clear that any fuel usage loses are more than made up for by tonnage increases.

ML

  • Member since
    May 2013
  • 3,231 posts
Posted by NorthWest on Friday, July 18, 2014 9:57 PM

Thanks, Don. I was struggling to find the best words to explain it!

Fairbanks-Morse was the only builder to make use of concrete as ballast in locomotives.

  • Member since
    September 2013
  • 2,505 posts
Posted by caldreamer on Saturday, July 19, 2014 5:16 PM

I would still like to kno wwhat the starting continupous tractive efforts are for the SD70Ah and ES44AH's.

  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Saturday, July 19, 2014 9:00 PM

200,000-216,000lbs depending on rail conditions.

ML

  • Member since
    September 2006
  • 158 posts
Posted by Bryan Jones on Sunday, July 20, 2014 12:46 AM

GDRMCo

200,000-216,000lbs depending on rail conditions.

An ES44AC or SD70ACe that has been ballasted to 432,000lbs and is also equiped with the High Tractive Effort software can only produce a maximum of 200,000lbs tractive effort. This is a software limitation. These units could produce more than 200,000lbs tractive effort but there is concern for wheel and rail damage.

While UP's SD70AH and C45AH's are equiped with extra ballast bringing the units in the 427,000-428,000lb range they lack the  High Tractive Effort software. In this case these units will only produce slightly more tractive effort than the standard weight SD70ACe's and C45ACCTE's on the UP roster. To reach the 200,000lb maximum tractive effort these locomotives would have to have both the additional ballast and HTE software. The CSX specification takes things a few steps further, requiring not only the additonal ballast and HTE software but rail conditioners and steerable/radial trucks.

AC traction locomotives are not the only ones to benefit from additional ballast, DC traction units also benefit. The whole heavy, high tractive effort locomotive program on CSX was inspired by a similar effort of the Western Maryland RR which had a pair of new SD40's ballasted to 420,000lbs in an effort to increase tractive effort/adhesion. This is why CSX chose to have its fleet of ES44DC's ballasted to 432,000lbs. In years past Burlington Northern had ordered SD40-2's weighing 425,000lbs and Chicago & North Western C40-8's weighting 420,000lbs, among others.

Bryan Jones

  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Sunday, July 20, 2014 2:54 AM

What happened to the 36K software then?

ML

  • Member since
    July 2014
  • 5 posts
Posted by UPMACHINIST on Tuesday, November 11, 2014 11:38 AM

Since a cubic yard of concrete costs around $80 and can weigh up to 4000 lbs then I would definitely say an $80 "investment" in more tractive effort from a multi-million dollar locomotive is "worth it".

  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Tuesday, November 11, 2014 11:42 PM
Extra thickness steel is used in the frame, there's no concrete in any newly built 'heavy' locomotive (CSX's AHs, NS's ACes and ES44ACs, the UP AHs, etc).

ML

  • Member since
    September 2010
  • 339 posts
Posted by efftenxrfe on Wednesday, November 12, 2014 6:38 PM

My first read of this thread just happened, and a statement in July of this year said that FM was the only user of concrete ballast.

Well, SP bought about 200 GP9's, in the 1950's, that had a circular, about 4 feet in diameter, steel cylinder about 3, maybe more, feet high. It lived in the short hood of the engs without steam generators.

The cylinders were full of concrete...

  • Member since
    November 2013
  • 1,097 posts
Posted by Buslist on Thursday, November 13, 2014 8:53 AM

oltmannd

 

 
NorthWest

AC locomotives are limited by their adhesion, their ability to grip the rail. Adding weight increases the adhesion.

 

 

 

You have the right idea, just some clarification on terms.

Adhesion is how well the wheel "sticks" to the rail.  It's expressed as the ratio of tractive force/locomotive weight - usually as a %.  An AC locomotive might have 35% adhesion.  How much tractive force (tractive effort) it can generate depends on it's weight.  The heavier, the harder it can pull.

 

 

in some of the original tests with the SD60MACs on Monument Hill adhesion levels as high as 45% were experienced.

  • Member since
    September 2013
  • 918 posts
Posted by Kyle on Tuesday, November 18, 2014 3:53 AM

A few extra tons on one locomotive is more efficant than running an extra locomotive

  • Member since
    August 2004
  • From: St. Paul, Minnesota
  • 2,116 posts
Posted by Boyd on Tuesday, November 25, 2014 11:33 PM

I think the front around the cab would be a better place to add metal. Construction companies sometimes use large 1" or so thick steel plates to cover holes in streets when they are working on utilities. One of them that is 8'x10' weighs several tons. 

Modeling the "Fargo Area Rapid Transit" in O scale 3 rail.

  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Wednesday, November 26, 2014 3:11 AM
Or simply build the frame from thicker steel to keep the weight better balanced...

ML

  • Member since
    January 2014
  • 202 posts
Posted by zkr123 on Wednesday, November 26, 2014 9:14 AM
So the SD70AH's are DC powered?
  • Member since
    June 2003
  • 1,009 posts
Posted by GDRMCo on Wednesday, November 26, 2014 10:57 AM
AC.

ML

  • Member since
    April 2014
  • 3 posts
Posted by sparks82 on Monday, April 6, 2015 8:18 AM
what does the AH represent in SD70AH ?
  • Member since
    October 2014
  • From: Flint or Grand Rapids, Mi or Elkhart, It Depends on the day
  • 573 posts
Posted by BOB WITHORN on Monday, April 6, 2015 10:40 AM
A/C traction and heavy frame. If you like letters, it probably should be SD70ACeH
  • Member since
    April 2014
  • 3 posts
Posted by sparks82 on Monday, April 6, 2015 3:05 PM

thank you :)

  • Member since
    May 2003
  • From: US
  • 25,292 posts
Posted by BaltACD on Monday, April 6, 2015 4:05 PM

When CSX used Dash-8's as their standard coal power, the normal size train was 90 cars.

When the AC's became the standard coal power, the normal train sized increased to 100 cars.

With the Heavy AC's being the standard coal power, the normal train size has become 110 cars.

Each increase in train size has permitted 1000 net tons of additional freight to be moved per train.  The revenues from additional tonnage per train mount up.

Never too old to have a happy childhood!

              

  • Member since
    September 2001
  • From: US
  • 9 posts
Posted by cozephyr on Friday, April 10, 2015 5:54 AM

Bryan Jones

 

 
GDRMCo

200,000-216,000lbs depending on rail conditions.

 

 

 

 

An ES44AC or SD70ACe that has been ballasted to 432,000lbs and is also equiped with the High Tractive Effort software can only produce a maximum of 200,000lbs tractive effort. This is a software limitation. These units could produce more than 200,000lbs tractive effort but there is concern for wheel and rail damage.

While UP's SD70AH and C45AH's are equiped with extra ballast bringing the units in the 427,000-428,000lb range they lack the  High Tractive Effort software. In this case these units will only produce slightly more tractive effort than the standard weight SD70ACe's and C45ACCTE's on the UP roster. To reach the 200,000lb maximum tractive effort these locomotives would have to have both the additional ballast and HTE software. The CSX specification takes things a few steps further, requiring not only the additonal ballast and HTE software but rail conditioners and steerable/radial trucks.

AC traction locomotives are not the only ones to benefit from additional ballast, DC traction units also benefit. The whole heavy, high tractive effort locomotive program on CSX was inspired by a similar effort of the Western Maryland RR which had a pair of new SD40's ballasted to 420,000lbs in an effort to increase tractive effort/adhesion. This is why CSX chose to have its fleet of ES44DC's ballasted to 432,000lbs. In years past Burlington Northern had ordered SD40-2's weighing 425,000lbs and Chicago & North Western C40-8's weighting 420,000lbs, among others.

 

Bryan Jones

 

Appreciated your clarification on this subject.

  • Member since
    December 2008
  • 28 posts
Posted by monon99 on Monday, April 13, 2015 8:06 PM

The heavier weight provides maximum speed on the maximum grade with maximum tonnage. Its purpose is to speed up heavy trains on slow heavy gradient territories.

the real question is what is the point in building any SD70? These are pathetic slippery, painfully noisy droning engines with a solid cab and bouncy make you vomit engines with the isolated cab. Adhesion is a joke, verifiable only in perfect lab conditions. The reality is that they slip and spin and lose speed and stall because the computer won't let a whiskered hogger apply sand at the right time. Then there's the obnoxious loud bell warning that the lights will turn off soon followed by the stupid bell ringing warning that the lights actually will turn off now just to make sure you don't get that desperate safety nap.

 

Join our Community!

Our community is FREE to join. To participate you must either login or register for an account.

Search the Community

Newsletter Sign-Up

By signing up you may also receive occasional reader surveys and special offers from Trains magazine.Please view our privacy policy