Posted by rjemery on Saturday, February 5, 2011 10:29 PM

The recent cold snap in the American Southwest caused New Mexico's Rail Runner service to be curtailed.  According to reports, the single digit temperatures (Fahrenheit) caused the rails to contract, making for an unsafe running condition.

I am curious about what specifically was or is the problem.  Other rail lines in the western states apparently did not shut down because of the cold weather.

More generally, how are tracks constructed and maintained to permit safe running from below zero temperatures to above 100 degree temperatures?

RJ Emery near Santa Fe, NM

  • Member since
    December 2007
  • 1,307 posts
Posted by Falcon48 on Sunday, February 6, 2011 12:17 AM

rjemery

The recent cold snap in the American Southwest caused New Mexico's Rail Runner service to be curtailed.  According to reports, the single digit temperatures (Fahrenheit) caused the rails to contract, making for an unsafe running condition.

I am curious about what specifically was or is the problem.  Other rail lines in the western states apparently did not shut down because of the cold weather.

More generally, how are tracks constructed and maintained to permit safe running from below zero temperatures to above 100 degree temperatures?

I'm not a track engineer.  But my guess is that the problem wasn't the cold temperature as such, but a large, rapid drop in temperature.

  • Member since
    December 2001
  • From: Northern New York
  • 25,011 posts
Posted by tree68 on Sunday, February 6, 2011 2:34 AM

Pull-aparts, either due to broken rails or at joints, are all too common when it gets cold. 

While the rail is designed to expand and contract, there are limits.  Pull-aparts are the opposite of sun kinks.

LarryWhistling
Resident Microferroequinologist (at least at my house) 
Everyone goes home; Safety begins with you
My Opinion. Standard Disclaimers Apply. No Expiration Date
Come ride the rails with me!
There's one thing about humility - the moment you think you've got it, you've lost it...

  • Member since
    August 2006
  • From: South Dakota
  • 1,592 posts
Posted by Dakguy201 on Sunday, February 6, 2011 5:15 AM

When the rail is laid, it may be heated to a specified temperature.  This becomes its neutral temperature; the point at which it is neither trying to expand nor contract.  Thereafter the rail is attempting to kink or pull apart depending on the relationship of actual rail temperature to the neutral temperature.  Presumably rail laid in the desert southwest will have a higher neutral temperature than that in the Midwest, even when owned by the same railroad.    

  • Member since
    July 2003
  • From: Sierra Vista, Arizona
  • 13,757 posts
Posted by cacole on Sunday, February 6, 2011 9:25 AM

Passenger safety -- Rail Runner is a commuter line, so the officials that be are probably more concerned with passenger safety due to broken rail.

  • Member since
    January 2003
  • From: Kenosha, WI
  • 6,567 posts
Posted by zardoz on Sunday, February 6, 2011 12:29 PM

Dakguy201

When the rail is laid, it may be heated to a specified temperature.  This becomes its neutral temperature; the point at which it is neither trying to expand nor contract.  Thereafter the rail is attempting to kink or pull apart depending on the relationship of actual rail temperature to the neutral temperature.  Presumably rail laid in the desert southwest will have a higher neutral temperature than that in the Midwest, even when owned by the same railroad.    

Correct.  The rails there would have been laid to withstand higher temperatures, which would occur much more frequently than such cold extremes.

When Mudchicken gets here, he will give us the final answer.

  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Sunday, February 6, 2011 12:34 PM

tree68

Pull-aparts, either due to broken rails or at joints, are all too common when it gets cold. 

While the rail is designed to expand and contract, there are limits.  Pull-aparts are the opposite of sun kinks.

cacole

Passenger safety -- Rail Runner is a commuter line, so the officials that be are probably more concerned with passenger safety due to broken rail.

Building off these two posts, up here in Massachusetts, the MBTA runs with restricted speeds whenever the temperature gets into the upper 70s. The neutral temperature is colder, so we can run at normal speed most of the time in the winter.

  • Member since
    October 2008
  • From: Calgary
  • 2,047 posts
Posted by cx500 on Sunday, February 6, 2011 7:47 PM

The rail, as already stated, is under a great deal of tension when the temperature drops well below the neutral temperature.  Especially if the rail is new and recently laid, the first really cold snap can find any trivial imperfection in the rail or welds.  It's a miserable job for the track forces, who get called out, often in the middle of the coldest night of the year, to get the railroad running again.

John

  • Member since
    January 2010
  • 538 posts
Posted by WMNB4THRTL on Sunday, February 6, 2011 7:50 PM

How do they fix something like that?!

Nance-CCABW/LEI 

“Even if you are on the right track, you’ll get run over if you just sit there.” --Will Rogers

Whether you think you can, or you think you can't, you're right! --unknown

  • Member since
    March 2016
  • From: Burbank IL (near Clearing)
  • 13,540 posts
Posted by CSSHEGEWISCH on Monday, February 7, 2011 6:50 AM

WMNB4THRTL

How do they fix something like that?!

A common starting point is to lay a rope soaked in kerosene or diesel oil next to the rail and light it.  The heat causes the rail to expand back its appropriate length.

The daily commute is part of everyday life but I get two rides a day out of it. Paul
  • Member since
    June 2003
  • From: Northern New Mexico
  • 465 posts
Posted by rjemery on Monday, February 7, 2011 8:56 AM

In very cold weather, I assume the rail contraction is localized.  Otherwise, track workers would have to lay miles and miles of burning rope.  Is the contraction problem most prevalent around switches?

Another question:  In very hot weather, how long does it take for kinks to form?  Is kinking a gradual process, or does stress build to the point that the rail just kinks in a matter of seconds or minutes?  If one rail kinks, does the other follow?

RJ Emery near Santa Fe, NM

  • Member since
    September 2002
  • 762 posts
Posted by kolechovski on Monday, February 7, 2011 9:09 AM

With heat kinks, since both tracks are tied together through the wooden or concrete tie, they do go together when a heat kink occurs.  Heat kinks are much rarer when there is sufficient ballast to hold the tracks in place, but if there is insufficient ballast, worn-down ballast, no ballast at all (freshly laid track), or severe heating, like in desert conditions, heat kinks are common.  Usually, it is a sudden thing that happens, as the sideways forces from rail ends pushed against each other finally overcome the hold of the ballast, and a part of the track then jets sideways to relieve the pressure.  This is why with continuous rail, there are still occasional joints-it's to give the rails some room to expand without pushing sideways.  About all that can be done is preperation for the environment a track will be laid (setting the right neutral temp at time of laying), and patrols during hot summer months.

In case you're wondering, derailments have happened from joints not having enough room between the rails, and one rail then climbs higher than the one in front of/behind it during expansion.  As for the sideways kinks, anything can still usually make it through at slow speed with advance warning, though usually maintenance is called to deal with them instead.

  • Member since
    October 2006
  • From: Allentown, PA
  • 9,810 posts
Posted by Paul_D_North_Jr on Monday, February 7, 2011 9:59 AM

Falcon48

 rjemery:

The recent cold snap in the American Southwest caused New Mexico's Rail Runner service to be curtailed.  According to reports, the single digit temperatures (Fahrenheit) caused the rails to contract, making for an unsafe running condition.

I am curious about what specifically was or is the problem.  Other rail lines in the western states apparently did not shut down because of the cold weather.

More generally, how are tracks constructed and maintained to permit safe running from below zero temperatures to above 100 degree temperatures?

 

I'm not a track engineer.  But my guess is that the problem wasn't the cold temperature as such, but a large, rapid drop in temperature.  [emphasis added - PDN] 

 

That's it, I suspect.  Cold temperatures that are attained over a period or a couple days aren't usually as much of a problem - esp. when there are heavy freight trains running over the line to shake things up from time to time and sometimes prevent concentrations of stress at a point (and sometimes aggravate that effect !). 

Also, if some portion of the track is fairly new, and this was its first encounter with temperatures that cold, there might have been a good reason for an abundance of caution about that condition serving as a real-life testing procedure for finding the 'weak links' in the chain of rails, until it became clear that all of the rail and joints survived intact.  And/ or if the officials had some reason to doubt the integrity or quality of their track system, esp. the rail's neutral temperature and the rail fastenings, etc. . . . Whistling  some precautions might have been in order. 

But if the Rail Runner has a conventional track circuit-based signal system, any rail break should show up immediately as an open or incomplete circuit.  That usually results in either a red indication or dark signal condition, so there would be some warning of it - unless it happened right underneath or in just in front of the train - see first paragraph above . . . .   

The rail anchors and/ or clips that are used to secure the rails to the ties can be pretty effective in restraining the motion that's induced by temperature changes - contraction for colder, expansion for hotter - and a rule of thumb is that 200 ft. to 400 ft. at the ends of a CWR strong is usally enough.  It's been a while since I did the calculation for the induced stress caused by temperature changes, but I'm certain that any reasonable temperature range in the US will not break a rail in good condition, without something else going on that affects it.

When a pull-apart does occur, a temporary fix - if the break is fairly clean and near vertical - is to apply/ install a pair of joint bars, drilled and bolted on one or both sides of the break, and then apply/ issue a Slow Order for the trains, depending on the size/ length of the break and its location - tangent track or curved, turnout, yard or main line, etc. 

- Paul North. 

"This Fascinating Railroad Business" (title of 1943 book by Robert Selph Henry of the AAR)
  • Member since
    October 2008
  • From: Calgary
  • 2,047 posts
Posted by cx500 on Monday, February 7, 2011 11:52 AM

CSSHEGEWISCH

 

 WMNB4THRTL:

 

How do they fix something like that?!

 

 

A common starting point is to lay a rope soaked in kerosene or diesel oil next to the rail and light it.  The heat causes the rail to expand back its appropriate length.

It will depend on how large the gap is, which in turn is affected by how well the rail anchors were applied and maintained. 

If the gap is small, heating it as described may be enough but you might need to warm the rails to as much as 120F above air temperature in the middle of a howling blizzard.  First though you drill holes in both ends so a joint bar can be applied once the gap closes.  It will be advisable to adjust the rail anchors immediately afterward, re-applying any that might have been removed to help the rail grow.

Another method is to cut out a piece and insert a short piece of rail, perhaps 20 feet long with joint bars at each end.  The shape of the break can be a factor in deciding which method to use.

Either way, there is more work to be done in the spring before summer heat becomes the concern.  The joints need to be field welded and the rail restressed to the proper neutral temperature.  If a piece of rail has been inserted you need to keep track of how big the gap was in the broken rail since the replacement rail is now too long by that amount.

John

  • Member since
    December 2001
  • From: Sunny (mostly) San Diego
  • 1,920 posts
Posted by ChuckCobleigh on Monday, February 7, 2011 4:23 PM

For an in-depth discussion of the topic of "neutral temperature" check this link out for the NTSB report on the 2002 Autotrain sun kink derailment.  The really interesting stuff starts at about page 43 of the report.

One interesting point is that over time, the neutral temperature of a length of CWR can change due to various things, which is probably a phenomenon that give folks like our muddy feathered friend a lot of work.

  • Member since
    July 2006
  • 2 posts
Posted by nkp766 on Monday, February 7, 2011 5:18 PM

A few of these replies have mentioned sun kinks.  Check out

http://www.trainorders.com/discussion/read.php?11,2119294 for a discussion and a photo of a sun kink.  If not a trainorders member the photo will be small.

  • Member since
    October 2006
  • From: Allentown, PA
  • 9,810 posts
Posted by Paul_D_North_Jr on Monday, February 7, 2011 10:04 PM

Thanks Chuck, for that link.  From the bottom of page 29 of that NTSB Auto-Train accident report, under "CWR Temperature Control" [emphasis added - PDN]: 

"When the longitudinal mechanical and thermal compressive forces in CWR build to a point at which they exceed the track structure's ability to restrain them, a track buckle will occur.  According to AREMA, the magnitude of force that may be developed within CWR, independent of its length, is the product of the difference in temperature between the neutral rail temperature [61] and the current rail temperature, multiplied by the cross-sectional area of the rail and the factor of 195 pounds per square inch (psi). [62]  In the daytime, rail temperature is commonly about 30° F above the ambient temperature. 

[61] This is the same as the anchoring temperature.

[62]

 

The internal stress of restrained rail is the product of the coefficient of expansion and the modulus of elasticity of the steel, times the change in temperature."

 

 

 

 

"This Fascinating Railroad Business" (title of 1943 book by Robert Selph Henry of the AAR)
  • Member since
    December 2001
  • From: Sunny (mostly) San Diego
  • 1,920 posts
Posted by ChuckCobleigh on Tuesday, February 8, 2011 1:21 AM

Paul_D_North_Jr

Thanks Chuck, for that link.  From the bottom of page 29 of that NTSB Auto-Train accident report, under "CWR Temperature Control" [emphasis added - PDN]: 

"When the longitudinal mechanical and thermal compressive forces in CWR build to a point at which they exceed the track structure's ability to restrain them, a track buckle will occur.  According to AREMA, the magnitude of force that may be developed within CWR, independent of its length, is the product of the difference in temperature between the neutral rail temperature [61] and the current rail temperature, multiplied by the cross-sectional area of the rail and the factor of 195 pounds per square inch (psi). [62]  In the daytime, rail temperature is commonly about 30° F above the ambient temperature. 

 

[61] This is the same as the anchoring temperature.

[62]

 

 

 

The internal stress of restrained rail is the product of the coefficient of expansion and the modulus of elasticity of the steel, times the change in temperature."

That discussion time-warped me back to the materials and solid mechanics classes I had to take in the "basic general education of engineering" that even us haughty EEs had to take.  (I don't think that a lot of EE curricula today require that broad of an engineering study, which may or may not be good, but that's a whole other issue.)  In my career, stress and strain referred to milestones, budgets and deliveries and the management that impeded progress, not the mechanical terms that were actually pretty interesting when I was studying the stuff.

One interesting thing that enlightened me in the NTSB report this time around was the discussion of rail anchors.  I hadn't realized how far down they project, since I had only observed them in-place and thus didn't appreciate how much bearing surface actually comes into contact with the ties.  Now it makes sense how much utility the anchors really have.  You learn something new every day, in spite of your best efforts.

  • Member since
    August 2004
  • From: St. Paul, Minnesota
  • 2,116 posts
Posted by Boyd on Wednesday, February 9, 2011 11:14 PM

Now if someone could just design telescoping track that problem would be solved. I'd like a tape measure with no tape but instead a holographic tape. A holographic tape would never bend and fall to the ground after being extended out 12 feet,, it would just extend forever.

 

Modeling the "Fargo Area Rapid Transit" in O scale 3 rail.

  • Member since
    October 2008
  • From: Calgary
  • 2,047 posts
Posted by cx500 on Thursday, February 10, 2011 4:06 AM

Boyd

Now if someone could just design telescoping track that problem would be solved. I'd like a tape measure with no tape but instead a holographic tape. A holographic tape would never bend and fall to the ground after being extended out 12 feet,, it would just extend forever.

 

I have seen slip joints used on transit lines, usually near changes in track structure or bridges I think. One side is like a switch point, and the other rail can slide against it.  So telescoping track has already been designed.  I suspect slip joints may also have been used very occasionally on freight roads at critical places such as a movable bridge.

John

Join our Community!

Our community is FREE to join. To participate you must either login or register for an account.

Search the Community

Newsletter Sign-Up

By signing up you may also receive occasional reader surveys and special offers from Trains magazine.Please view our privacy policy