Trains.com

Subscriber & Member Login

Login, or register today to interact in our online community, comment on articles, receive our newsletter, manage your account online and more!

roadway to yard transition

4033 views
20 replies
1 rating 2 rating 3 rating 4 rating 5 rating
  • Member since
    November 2010
  • 2 posts
roadway to yard transition
Posted by glastar on Saturday, November 27, 2010 10:06 PM

what is the best way to transition from mainline roadbed rail hieght into the switch yard?  there needs to be some kind of transition to table top level.  Or raise the entire yard to roadway level.  how about a gentle cookie cutter slope to table top level.  what's to most accepted method?

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Saturday, November 27, 2010 11:10 PM

There is no "best way" to make a yard transition.  The real railroads did any number of things that worked for the particular location, and there are an equal number of model railroads that did the same.  If you are modeling a specific prototype location then follow the pattern they used, othewise do whatever is easiest for you to accomplish the task.  Nobody is going to know the difference and the only one you need to satisfy is yourself.

Any of the methods you mentioned will work just fine, and I've also seen the real railroads just use a sudden drop from mainline to yard, nothing fancy in track geometry or splicing, as the following photos show.

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 7:04 AM

Wonderful pictures!  Big Smile

The big thing that the real RR try to achieve that it is best to copy is to keep the railheads level across the track.  If this can't be done the rail that will usually be higher is the one on the outside of the curve.  There are examples of the opposite - sometimes caused by lack of maintenance or subsidence - but they are likely to be problem areas and movements will be extremely slow to try to avoid cars' wheels climbing the rail and derailing.

In a similar vein it is preferable to avoid beginning the change of grade until as far beyond the common crossing (frog) of the switch as possible.  Again there are examples of the grade changing even right in the switch... I would not try to model that.

The best plan is to keep things as geometrically simple as possible.

You don't actually have to alter the level up or down in a model.  Apart from the fact that real yards could remain at the same level as the main track you can achieve a visual illusion by changing the colour(s) of the ballast and surrounding ground.

Another thing to consider is that when main track is re-ballasted - which is a main cause of the increased height of main track - the RR normally work on the plain track seperately from switches.  Switches are much more complicated for re-ballasting and ballast cleaning - even for just tamping.  It is important to maintain the geometry of the switch. 

When a switch is worked on the work doesn't just affect the one track.  If any change is made in the height (or any other orientation) of the switch this will require work on whatever it is connected to.  This is more work and more down time.

Switches may have their level (or other factors) changed but it will show up in whatever they are connected to.  this is likely to include an element of new/cleaned ballast for a distance in the diverging track.  While the work is going on it may mean that the diverging track is temporarily disconnected.  Provided the change will not affect the main track the diverging track may be raised (or lowered) to the new position ahead of the main track.  When the main track is altered there may still be a period when the side track isn't re-connected.  This would usually be short... unless a problem has arisen.  Of course the side track may be disconnected and the main track altered first with the side track being "corrected" to meet it later.

Something that goes with this is that out-of-use tracks may be at different levels to in use Main tracks.  Clearly repeated top ups of Main track may raise the main track above even out-of-use main tracks as well as yards and sidings... but the reverse may happen if a main track is lowered... as when a route is adjusted to take taller trains like double stacks... which is a more specialised issue.

However... Main Track doesn't just have to be maintained in a way that preserves vertical links with side and other tracks... it also has to keep to clearances over and under bridges, through tunnels and sideways with platform faces (where they are raised) and tunnel and bridge sides.

So... back at the switches... it can be easier and/or necessary for the MoW to keep the switches at one level and bring the main track up or down to/from the switches.  For a modeller this will of course mean that he has to sort out two changes of level  - in the main track on each side of the switch -instead of one in the yard... (Mischief)  However this can be simplified by where the switch is in the scenicked area...

I would be inclined to consider putting the variation in the main track rather than the yard as a possible source of adding visual interest to trains running on the Main... provided I wasn't planning to leave cars standing on the Main... which really is an entirely different subject...

Cool

Cool

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Sunday, November 28, 2010 7:34 AM

Good analysis Dave, but I would add from real world experience that it is nearly impossible to LOWER track to meet a geometry requirment.  Lowering track usualy can only be done during an undercutting operation which is complex, slow and very expensive.   A UNIMAT tamper such as an 08-16/3S makes short work of tamping a switch so that is no problem.   For all practical purposes, track is always lifted to correct geometry errors and ballast added as required to fill any vacant cribs. 

Tamping a switch is no problem, note from the photo the heads telescope out and the entire unit can swivel as well as allowing independent control of each head.   Rollers or hooks can be used to clamp the track so there is no problem at all tamping through the frog and points.

 

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

  • Member since
    February 2010
  • 88 posts
Posted by TexasSP on Sunday, November 28, 2010 8:45 AM

So is it safe to say from what is gathered here that most likely two track sections that have a great difference in level now could have been a lot closer to the same level 60 years ago?

Meaning mainlines that appear much higher now that unused or little used sidings may not have been that way originally?

Thanks for all the info!

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Sunday, November 28, 2010 9:10 AM

Yes, it is perfectly safe to say that.  One track may have been used more than the other, or one is newer than the next so one might have more ballast underneath due to repairs over time.  For the most part in order to get a good geometry correction and stable ballast tamp you have to lift the track a minimum of 2" (roughly the diameter of the ballast stone you are using) even on the tangent.  In fact, in the begining yards were the same elevation as the mains, but over the years the mains got repaired, the yards (and sidings) didn't, so on some tracks I've seen the yards can be quite a bit lower than the mainlines and normaly the only time the yard lead gets tamped is when the mainline switch is repaired or tamped or there is a new piece of equipment they want to test so they use the yard lead for experiments (it's a way to get a "free" tamp or tie replacement of the yard lead).  So figuring very roughly a 2"  lift about every 5 to 10 years on the mains, minus a bit for settling over time, in 60 years you could have 12-24" of elevation added.  This is particularly worrysome where catenary is involved, but that is a different animal all the way around.

Remember when it comes to track repair the railroads are cheap, I don't mean "thrifty" I mean CHEAP with a capital C.  Since yards are for storage of equipment, sorting of trains etc, and all of it is a speeds of less than 10mph, the quality of track is not very important and it can deteriorate quite a lot before it needs something done to it.  I've tested tampers in some yards that I won't name (but will remain BNSF) that were so bad when you tried to lift the track it pulled the rails off the ties.  The yard tracks start at the last long tie of the divergent route of the switch, at that point the track can change very suddenly from nice to junk depending on the age of the yard.  

So with all that said, unless you are modeling a particular place on a particular prototype, you can feel free to do just about anything you want with your track and you can justify it because somewhere, sometime, a full sized railroad probably did it.

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

  • Member since
    September 2003
  • From: Southeast Texas
  • 5,449 posts
Posted by mobilman44 on Sunday, November 28, 2010 9:24 AM

Hi!

Your question is timely as I just finished doing what you described on my HO layout. 

The mainlines are on the standard 1/4 inch roadbed.  As I did not want the yard to be on the tabletop plywood, I glued on a 3/32 (standard thickness from Office Depot cork rolls) as a base for the yard tracks.  I then decided to add a second layer, which left me about 1/16th of an inch from being level with the mainline tracks.  I took some cardstock and made a layered bevel for the remaining transition.

While it sounds like it would look "funny" with it all on the same level, it really doesn't.  The key is to keep about a 1/2 inch space between the roadbed and the sheet cork - kind of like a drainage ditch. 

By the way, the main reason I did this is that those grade transformations with (in my case) curves and turnouts involved, often give trouble down the road.  I've been there on the previous layout, and wanted to avoid it on this one.  I did, and it works.

 

ENJOY  !

 

Mobilman44

 

Living in southeast Texas, formerly modeling the "postwar" Santa Fe and Illinois Central 

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 11:12 AM

" ...it is nearly impossible to LOWER track to meet a geometry requirment. "

No it isn't  Mischief it's just exhorbitantly expensive!  ,,, Which I'm sure that you will agree is why they make very certain that they get the geometry right approaching anything like a tunnel where the clearances are tight.  On the other hand I have known a lot of cases where they have opted to raise bridges as the far cheaper option... mainly when installling overhead cables.

I don't think that I actually meant an option of lowering (???) What I meant was that, rather than have to do a lot of messing about they are quite likely to keep a switch or other "fixed feature" where it is and make a slope down into and up from it to the new level in the plain track on either side.

Certainly modern tampers can do "wonders" (so long as the computerisation doesn't get messed up) but this has only been the case relatively recently.  In particular track maintained by lots of shovels was a different world.  (In some ways it was better - so long as it wasn't you pushing the shovel all day/night).

Hope this clarifies.

Cool

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 11:13 AM

oops!  posted twice...

WHERE'S THE DELETE OPTION GONE?

Cool

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Sunday, November 28, 2010 11:20 AM

Yes, you are quite correct.  Ramping in and out of a fixed feature such as a bridge or road crossing is quite common.  The idea is to build such a feature higher than the trackage so over time the rest of the line will rise to meet it.  I've not seen it done much with a switch, since as you say modern tampers can do wonders with them and it's no big deal anymore to tamp right through them.  The only difficulties I've encountered were at interlockings like Bridesburg station in Philly where some new construction was put in where the rails were cut too long and by lifting one switch it pulled the opposite switch out of line- but thanks to the modern miracle of AGGS the defect was quickly found and corrected.

And for the old days of shovels and track bars- well, it paid the bills and built character Laugh

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

  • Member since
    July 2006
  • From: Chamberlain, ME
  • 5,084 posts
Posted by G Paine on Sunday, November 28, 2010 12:40 PM

One reason that sidings and yards are at a lower level from the main line is to reduce the possibility of a car rolling from the siding/yard on to the main line.

I saw a hopper get away from the yard crew at the power plant coal dump at a shipyard I worked at many years ago.Surprise I was surprised at how quickley the car picked up speed. The crew would spot the cars with wood wedges blocking the wheels, and with the brake off. When it was time to move the car, they would remove the wedges and roll it onto the coal dump. When it took off, one guy Cowboy jumped on the car and put on the brakes using the handwheel. He was followed by one of the shipyard's Brownhoist cranes blowing it's whistle to warn people that something was coming fast.

On my HO scale layout, I use cork roadbed for the mainline which is 1/4" and 1/8" sheet cork cut to roadbed width for the siding. I transition from mainline to siding by running the cork roadbed for 4 or 5 inches beyond the beginning of the transition and shave it into a ramp with a Surform block plane file.

George In Midcoast Maine, 'bout halfway up the Rockland branch 

  • Member since
    July 2006
  • From: 4610 Metre's North of the Fortyninth on the left coast of Canada
  • 9,352 posts
Posted by BATMAN on Sunday, November 28, 2010 1:31 PM

I just lower my cork into the foam. I find it much quicker and easier to do than grinding down the cork. Any errant gouges are quickly filled by the caulk. I find it easier to get a nice transition that's more even as the surface of the cork does not change. Sometimes when grinding down the cork I would end up with some dips and bumps. But not with this method. If you have plywood for a base you can use a chisel and mallet to do the same thing.

 

                                                                                     Brent

Brent

"All of the world's problems are the result of the difference between how we think and how the world works."

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 2:00 PM

Hmmmmm Hmm

I'm not going to say that building a yard lower than the Main will not stop a runaway from getting out... but (If it were my RR) I would like it to be a lot lower to achieve that.  It is surprising how much speed a car can pick up in a short distance.  Clearly a loaded car will get going better on a down grade... but an empty (even on a slight upgrade) with a good puff of wind behind it or, better still, at just the right angle for it to "tack" like a sailboat... well then you have an interesting situation.  A couple of feet would probably not do much to hold back a boxcar or anything similar that the wind could get hold of.

I have known one or two instances of cars "getting away".  They have usually escaped on down grades but, given the chance to get up a bit of speed they will go a long way up a following adverse grade... until eventually they will come to a stand (provided they don't go over a top and start down the next down grade)... however, once they have stopped on an upgrade they will come back... gathering speed as they do.  So long as they aren't going to hit anything the best thing to do is to let them sort themselves out.  This "upsets" management but if they want to try a flying tackle with several tons of moving metal they are welcome to.

The best thing to do with any runaway car is to drop it in the dirt... or a sand drag if you are somewhere "posh".  Derails do their job but tend to damage a car more than letting the planet stop it.

One thing to model inline with a drop-off is the flange marks in the ties(if they are wood).  you can kick the ballast back into place but you can't get rid of deep dents in ties.  (Not that I've ever... Whistling )  (Concrete ties "chip" on the approach side(s) if the ballast is lower than the tie top and/or not firmly compacted around the tie).  (That becomes approach sides if the cars are dragged back).  You can drag as many as 25 cars back on if you go steady... I'm told. Mischief

You can also re-rail almost anything with appropriately placed piles of fishplates provided that the wheels are close to the rail and almost in line with it.  The thing not to do is back up too far and put the other end off the track.  This tends to cause a distinct chnage of colour in the faces of those involved...  (And if you happen to be watching don't laugh too obviously unless you want to run from a shower of ballast)

Meanwhile, back at the different levels...  Someone said that one road in use may get more maintenance than another causing it to rise... this is also likely to cause the ballast to have a distinctly different appearance due to there being more newer/cleaner and/or different ballast in it.  The raised road may also have a looser "texture" and be much more free of contaminants... the reverse of which is that the less worked road may have settled down more, be more "compacted" and have more contaminants including weeds.

On the issue of yard maintenance.  RR do not want yard track to get bad - although I have been stunned by the condition of some yard track that has still had traffic working over it - bad track risks derailments which can damage cars, customers' loads and tie up the system.

There is therefore a balance to be achieved between the cost of maintenance and the risks of defering it.  There are also issues connected with balancing the availability of yard tracks to do what they are there for and having them out of use for maintenance.  A lot will depend on what the track is earning and what the disruption/cost of maintaining it will be.

Cool

 

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 2:16 PM

Something else I intended to mention... If you have a track still in use next to dead track it may not only be at a higher level but it may get re-aligned to a better curve... this may cut into the "territory" of the out-of-use line.  It's a detail but it's one of those things that can be used to add "history" to a scene.

Dead tracks are just dead tracks but a re-alignment shows that new money has been invested to improve the working track... and, potentially, to permit a higher line speed.

A re-alignment is quite a big job - even over a short length of track.  A RR will tend to prepare as much of the site as possible without affecting traffic before taking a few days - if possible only a weekend - to rip out the old track/alignment and install the new.

I was on a job where an office person (read "complete idiot") had planned to shove about 250 yards of track sideways into the position of a new curve using bulldozers.  Shall we be polite and say that "this was not going to happen".  Even if the ballast had been shovelled out from between the ties there was too much weight/friction/mass etc in the track that had been in place for at least ten years.  Track is designed to stay in place sideways as well as lengthways - and vertically.  The comments of the engineer in charge on site were (shall we say)  "quite colourful"... and then someone dug through a water main LaughLaugh

That reminds me of another thing...

Most track alignments will have some element of drainage aligned with them.  this means that to change the track alignment you have to change the drains in the free ground first. and you will have to change any drains affected by the track you are moving between ripping out the old and starting to put in the new.  all this will mean that there will be new drainage materials and works lined up ahead of the track being changed.

If there are any signal or power routes they may have to be changed as well.  Sometimes any through-routed cables are cut well clear of the work, a diversion is built well round the work site and then the cables are cut back into the original route well beyond the job.  This "diversion" sometimes becomes permanent and other times is replaced with new work close to the new track position.  All these things show as phases of work and changes in the materials used... and the state of its "weathering".

A really big job (although the site may be small) may include changes in any signals.  One reason for this can be that the signal just has to move sideways with the track shift... but if line speed is increased it can cause a complete relocation of the signal to accomodate sighting the signal by the Engineer and longer braking distances.

When relocating a signal you must not put up a new one (or parts of it) in a place that will cause it to hide the existing one.  This can make for replacement /altered signals having to be quite a bit more elaborate than the earlier example.  A plain post may get replaced with a signal bridge... or - if that has already happened - a bridge may be able to be replaced with a plain post.  If the signal base (concrete plinth) isn't going to get in anyone's way it may be left in place.  (I have also seen - and got pics somewhere - the lumps of concrete ripped out and dumped at the side out of the way).

Sometimes the control boxes and/or battery houses get shuffled about and sometimes they are replaced... again they can be piled to one side until they are removed for recycling or scrap.

The main considerations are to get as much work safely done ahead of the "Big Day" as can be done without disrupting traffic to keep the work on the Big Day short and simple.  Then the BIg Day/weekend will see the essential work done in one big effort (if possible).  After that anything that can be tidied up later will be sorted out in the same safe way as the preperation work with as little disruption to traffic as possible.

Bear in mind that if it is worth spending the money to make a major improvement in a track it will be carrying - or possibly be being planned to carry - pretty heavy traffic.  One train-a-day tracks don't (usually) get altered much...

On the other hand... if the County want to put in a new road... maybe with a bridge instead of a grade crossing...

Of course...

If you have taken out a connection (switches) or a diamond you may no longer need your main track to meet the level of the connection or diamond... So then you might raise the track by a considerable amount to improve things close by... or you may even go completely crazy and lower it!  This may result in signals having to be changed in height... and it may affect the drains...

So you can re-align vertically as well as sideways... or you can do both...

I think I'll go find a darkened room...

That should give you a couple of ideas to play with. Mischief

  • Member since
    May 2004
  • From: The Villages, FL
  • 515 posts
Posted by tcf511 on Sunday, November 28, 2010 7:51 PM

I do my transition a little different than has been mentioned so far. I have a yard that feeds into an industrial area and then out onto the mainline. My roadbed for the mainline is standard 1/4 inch cork. For the yard and industrial area, I laid out 1/4 inch sheet cork that I found online at a school supplies place. It comes in rolls that are 4' wide and various lengths. So I really have no change in height. To make the transition less obvious, I have my mainline hit the sheet cork in a scenery break that is a wooded area.

Tim Fahey

Musconetcong Branch of the Lehigh Valley RR

 

 

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Sunday, November 28, 2010 9:50 PM

Dave-the-Train

............  Someone said that one road in use may get more maintenance than another causing it to rise... this is also likely to cause the ballast to have a distinctly different appearance due to there being more newer/cleaner and/or different ballast in it.  The raised road may also have a looser "texture" and be much more free of contaminants... the reverse of which is that the less worked road may have settled down more, be more "compacted" and have more contaminants including weeds...."

You mean like this?

 

Dave-the-Train

On the issue of yard maintenance.  RR do not want yard track to get bad - although I have been stunned by the condition of some yard track that has still had traffic working over it - bad track risks derailments which can damage cars, customers' loads and tie up the system.

You mean like this?

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 10:48 PM

EEEK! 

That's impressive!  Thumbs Up

Got any more please?  Mischief

  • Member since
    July 2006
  • 2,299 posts
Posted by Dave-the-Train on Sunday, November 28, 2010 11:14 PM

tangerine-jack
  You mean like this?
http://im1.shutterfly.com/media/47a0cf04b3127ccefbe76882bc0100000030O08AbN2rVm4ctwe3nwY/cC/f%3D0/ps%3D50/r%3D0/rx%3D550/ry%3D400/

 I  most certainly do Smile  Although there looks to be little or no difference in height.  Do you know if the two  clean ballasted roads were done with a High Output Ballast Cleaner and the ballast topped up with an auto-ballaster set of hoppers?  It looks very much like they were.  Looking again it appears that the middle track has been completed by an HOBC while the far track has just had raised shoulders run in from a ballast train... the 4ft way is not just darker but the ballast is low to the tops of the ties.

Over on the right are the yellowed plants in a long line reeds or similar in a drainage dutch?

This is a superb shot for modern modellers. 

 

You mean like this?

http://im1.shutterfly.com/media/47a0cf04b3127ccefbe6c7d45de400000060O08AbN2rVm4ctwe3nwY/cC/f%3D0/ps%3D50/r%3D0/rx%3D550/ry%3D400/

 I  most certainly do Smile  again. Smile 

But notice the way that the scissors crossover, while on a grade, is almost all on one plane... at least it was before it was allowed to get in a mess.

I think that the yellow box near the front is a switch motor... is it to drive the near switch blades or is that a derail just this side of the tip of the blade?

What is the mesh/grid there for?  To prevent access by animals??

Are the large areas of yellowed grass with bits of green the result of weed killer spraying?  (It looks like it to me).

http://im1.shutterfly.com/media/47a0cf04b3127ccefbe7f4113dec00000030O08AbN2rVm4ctwe3nwY/cC/f%3D0/ps%3D50/r%3D0/rx%3D550/ry%3D400/

Nah Mischief  I've seen far worse than that!  The thing that I haven't figured out is how the bugs and beetles that eat out a rotted tie know exactly when to stop to leave a shell of wood so that the ballast doesn't collapse in on them.  Must be like miners working pit-and-stall.  Sometimes it looks more like the ballast is holding up the remains of the tie.

I like the way the switch has been plain lined by removing the switch blades and common crossing (frog).

I have seen thsi done in a low grade Main track here... with all the marks from the rail fixings still in the switch ties but ribbon rail run straight through,  In fact the curved rail had been taken out from the 4ft way of the main as well - but on the yard track alongside both curved rails were still in place (with no blade ends).  The yard track remained jointed track - so just a short length had been put in in place of the common crossing.

I love pics like these Big SmileThumbs UpStick out tongue

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Monday, November 29, 2010 1:22 AM

I think the worst of the lot is CN rails, one side is jointed, the other continuous, then it switches for a while to all jointed, then it will flip to the other side will be continuous and all the ties are covered in moss- you can never figure out which side of your fillings are going to be knocked out next!  A close second is the Bay Coast RR- 80 miles of 19 to 29ft jointed hell- makes you feel like a human pin ball ball at a blistering 10mph (with speed restrictions in certain places!)

Funny thing about the yard photo is that derailments are unheard of, but random uncouplings are common due to the sliding of the knuckles verticaly.  The switch was lined as it was because they needed the frog to repair a switch on the main so they stole one out of the yard.  In the real world you can have very bad track and still run a train, not so much in HO- if you had track like that in miniature nothing would run and it would be a simple static display.  But, oh if I could only simulate the sounds that stuff makes in miniature!

 

For to answer the questions, the ballast was dropped by a new Herzog ballast train with laser measuring and computerized hopper distribution and such (yet to be made to work properly).  The track at this time was wating to be tamped, but the multimillion dollar Herzog failed to drop ballast in the gauge.

Switch motor?  Are you kidding me?  It's the 0-5-0 e-manuel ground throw, it's yellow so you dont' trip on it.   The mesh and plywood is to keep you from falling into the water, that is the hinge point of the car float apron.  What is far more terrifying than the track here is the fact that it leads to a car float that is just as well maintained as the yard, for a real thrill ride you should drive something onto the car float, through the yard (hold breath)- across the 4" gap in the apron (pucker factor x6) and onto a 480ft car float which last saw maintenance sometime around WWI with no wheel stops on the far end (pucker factor x infinity/ pry fingers off brake handle/ change underwear).  I've got video of that somewhere.  I'll post it when I find it.

 

Weed killer?  Scoff, that stuff cost's money.  No, I took these photos in December- the calendar kills the weeds just fine.

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

  • Member since
    June 2007
  • From: Indiana
  • 3,549 posts
Posted by Flashwave on Monday, November 29, 2010 12:10 PM

Dave-the-Train

You can also re-rail almost anything with appropriately placed piles of fishplates provided that the wheels are close to the rail and almost in line with it.  The thing not to do is back up too far and put the other end off the track.  This tends to cause a distinct chnage of colour in the faces of those involved...  (And if you happen to be watching don't laugh too obviously unless you want to run from a shower of ballast)

Which is basicaly what they did with 4449's off pilot at Trainfest, she split the switch and they spent the good part of the night "shimming". And, onece thye got her up, they backed and dropped her pilot again off.

One more on the height of yards. Like they're saying, cars can speed up quite a bit, and no dip from one grade to anoither is going to stop a determined car under its own momentum. For example, Avon Yard sits on a bowl, with Indy to the east in the bottom of it. in the 90s, a string of cars got out of Avon, and foruntatley the tracks were cleared because they rolled ~20 miles into town, so far that a switcher from Hawthorne on the EAST side of Indianapolis was the closer engine to get them. And I think we remember the tragedy from a few years ago...

-Morgan

  • Member since
    August 2004
  • From: Virginia Beach
  • 2,150 posts
Posted by tangerine-jack on Monday, November 29, 2010 3:19 PM

Ok, now that we have discected to the Nth degree the reasons why track is at different heights, how does that relate to the topic of making a model RR transition?  IMHO grade changes in yards on the model is not required as it serves no purpose whatsoever from any operation standpoint (not counting a model hump yard- that's a different animal), but it adds visual interest and for that it's probably a good idea to lower the grade of the yards on a model RR.  The transition to the yard is determined by the space you have keeping in mind that our models are not as forgiving of track defects and wierd geometries as full sized trains are, so a smooth transition is a must.

Isn't model railroading more fun when you delve into understanding prototype operations and practices?  Now when people ask about your model yard you know how to believably BS them about real yards!

The Dixie D Short Line "Lux Lucet In Tenebris Nihil Igitur Mors Est Ad Nos 2001"

Subscriber & Member Login

Login, or register today to interact in our online community, comment on articles, receive our newsletter, manage your account online and more!

Users Online

There are no community member online

Search the Community

ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Model Railroader Newsletter See all
Sign up for our FREE e-newsletter and get model railroad news in your inbox!