Trains.com

Track construction and replacement around the world

1335 views
9 replies
1 rating 2 rating 3 rating 4 rating 5 rating
  • Member since
    December 2001
  • From: Denver / La Junta
  • 10,820 posts
Posted by mudchicken on Sunday, January 30, 2022 9:53 AM

Estonian panel party with Plasser and other western equipment. What Balt is thinking is inefficient is due to the super-heavy concrete ties that have to be moved by the gantry crane. 

Appears to be used for only replacing short sections of track which is probably fine for them. (Otherwise they would be flash-butt welding instead of Boutet welding)....The whole thing is done for existing track under traffic (and under catenary) with survey (optical robotics, GPS would be killed by multipath errors) as a a good check and verification for grade and alignment - the Plasser tamper has no idea where it is in the real world. Didn't really see it, but there appears to be a blade / dozer somewhere in the process that is also being guided by survey machine language. The whole process is small scale, out of face - the rail train enforces that.

I wouldn't be surprised if the old track panels were cascaded into a branchline or backtrack somewhere, at least the rail. Trying to figure out the Geogrid application and what the subgrade conditions dictated. (Peltier has apparently never been to the PRB during concrete tie construction - geogrid is everywhere along with the NEC trying to negate impact damage by concrete ties) . Like most of Europe, it's a little over-engineered, but its always been that way. Works for them. If that rail goes elsewhere, it's got to have the proper tie plates or concrete ties to properly work. Curious as to what triggered that particular piece of track to be replaced and the thinking that went with it.

I see the Burkhardt World Railways influence has not completely worn off.

Mudchicken Nothing is worth taking the risk of losing a life over. Come home tonight in the same condition that you left home this morning in. Safety begins with ME.... cinscocom-west
  • Member since
    December 2001
  • From: Denver / La Junta
  • 10,820 posts
Posted by mudchicken on Sunday, January 30, 2022 9:47 AM

Estonian panel party with Plasser and other western equipment. What Balt is thinking is inefficient is due to the super-heavy concrete ties that have to be moved by the gantry crane. 

Appears to be used for only replacing short sections of track which is probably fine for them. (Otherwise they would be flash-butt welding instead of Boutet welding)....The whole thing is done for existing track under traffic (and under catenary) with survey (optical robotics, GPS would be killed by multipath errors) as a a good check and verification for grade and alignment - the Plasser tamper has no idea where it is in the real world. Didn't really see it, but there appears to be a blade / dozer somewhere in the process that is also being guided by survey machine language. The whole process is small scale, out of face - the rail train enforces that.

I wouldn't be surprised if the old track panels were cascaded into a branchline or backtrack somewhere, at least the rail. Trying to figure out the Geogrid application and what the subgrade conditions dictated. (Peltier has apparently never been to the PRB during concrete tie construction - geogrid is everywhere along with the NEC trying to negate impact damage by concrete ties) . Like most of Europe, it's a little over-engineered, but its always been that way. Works for them. If that rail goes elsewhere, it's got to have the proper tie plates or concrete ties to properly work.

I see the Burkhardt World Railways influence has not completely worn off.

Mudchicken Nothing is worth taking the risk of losing a life over. Come home tonight in the same condition that you left home this morning in. Safety begins with ME.... cinscocom-west
  • Member since
    December 2001
  • From: Denver / La Junta
  • 10,820 posts
Posted by mudchicken on Sunday, January 30, 2022 9:40 AM

Estonian panel party with Plasser and other western equipment. What Balt is thinking is inefficient is due to the super-heavy concrete ties that have to be moved by the gantry crane. 

Appears to be used for only replacing short sections of track which is probably fine for them. (Otherwise they would be flash-butt welding instead of Boutet welding)....The whole thing is done for existing track under traffic (and under catenary) with survey (optical robotics, GPS would be killed by multipath errors) as a a good check and verification for grade and alignment - the Plasser tamper has no idea where it is in the real world. Didn't really see it, but there appears to be a blade / dozer somewhere in the process that is also being guided by survey machine language. The whole process is small scale, out of face - the rail train enforces that.

I wouldn't be surprised if the old track panels were cascaded into a branchline or backtrack somewhere, at least the rail. Trying to figure out the Geogrid application. Like most of Europe, it's a little over-engineered, but its always been that way. Works for them. If that rail goes elsewhere, it's got to have the proper tie plates or concrete ties to properly work.

I see the Burkhardt World Railways influence has not completely worn off.

Mudchicken Nothing is worth taking the risk of losing a life over. Come home tonight in the same condition that you left home this morning in. Safety begins with ME.... cinscocom-west
  • Member since
    March 2011
  • 188 posts
Posted by dpeltier on Thursday, January 27, 2022 9:58 PM

blue streak 1

Came across this rail replacement procedure apparently in Russia.  Very interesting use of track panels.  Old rail is sectioned into track panels and removed for apparently use elsewhere? 

Maybe, but probably that's just the most efficient way to get the material removed, regardless of whether it's then reused or simply scrapped.

blue streak 1

New panels installed but not joined.

The panel rails are jointed together (starts at 9:00) so that the rest of the panel train as well as the ballast train can get across

blue streak 1

Panel rail removed and long strips of welded rail installed.  Joining of long section thermited welded but joint bars installed as well.  Not trusting the Thermite  maybe because of temperature swings?

Pretty sure the joints are installed when the rail is laid, then time passes (right at the 33:20 mark), then the welders come by later, remove the bars and make the weld. There's no indication that the bars go back on after the weld is made. This "joint it now, weld it later" approach happens pretty often in North American practice as well.

blue streak 1

MC  Any experience of this type replacement?

Never seen it down exactly this way in a production environment. Then again, complete rebuild from the subballast up, including installation of a geogrid under the ballast layer, just isn't done on freight railroads over long distances and under traffic. The closest I've ever come was when we upgraded a 5,000' yard track to a main line. In that case we scrapped out the existing track in place, graded, and then built new track with a track-laying machine... But that was different because we could take the yard track out of service for a few weeks in the process.

More common for North American freight railroads is the P-811, which accomplishes something similar but is a continuous-production system. It doesn't require all that extra panel rail, but it also gives you a lot less opportunity to improve the ballast or any weak spots in the subgrade.

However, with that said... It's common at derailments to install as many track panels (jointed together) as it takes to plug the hole in the track. In some cases it's easier to relay the rail with a rail gang than to make a pair of welds every 40'. Same with some new construction projects where the length of track being built is too short to justify moving in a TLM, where access limitations favor panelized construction, and where the resulting number of panel joints would require an overwhelming number of welds.

Rail is crazy expensive and you hate to have to buy twice as much rail as you need, but the good thing is that a lot of the cost is recoverable as second-hand rail or even as scrap steel.

Dan

  • Member since
    December 2001
  • From: Northern New York
  • 25,009 posts
Posted by tree68 on Thursday, January 27, 2022 9:50 PM

Paul of Covington

   I liked the Flintstone-powered "speeder" at about 22:22.  What were they doing?  Track inspection?

Looked to me like a utility cart - carry tools and other supplies.

LarryWhistling
Resident Microferroequinologist (at least at my house) 
Everyone goes home; Safety begins with you
My Opinion. Standard Disclaimers Apply. No Expiration Date
Come ride the rails with me!
There's one thing about humility - the moment you think you've got it, you've lost it...

  • Member since
    May 2005
  • From: S.E. South Dakota
  • 13,569 posts
Posted by Murphy Siding on Thursday, January 27, 2022 9:47 PM

Paul of Covington

   I liked the Flintstone-powered "speeder" at about 22:22.  What were they doing?  Track inspection?

 

The scale of that makes the track look to be about 12-15" tall.

Thanks to Chris / CopCarSS for my avatar.

  • Member since
    July 2010
  • From: Louisiana
  • 2,310 posts
Posted by Paul of Covington on Thursday, January 27, 2022 9:16 PM

   I liked the Flintstone-powered "speeder" at about 22:22.  What were they doing?  Track inspection?

_____________ 

  "A stranger's just a friend you ain't met yet." --- Dave Gardner

  • Member since
    December 2001
  • From: Northern New York
  • 25,009 posts
Posted by tree68 on Thursday, January 27, 2022 8:49 PM

BaltACD
Looks very inefficient for what they are attempting to accomplish.

Men are cheap, equipment is expensive.

LarryWhistling
Resident Microferroequinologist (at least at my house) 
Everyone goes home; Safety begins with you
My Opinion. Standard Disclaimers Apply. No Expiration Date
Come ride the rails with me!
There's one thing about humility - the moment you think you've got it, you've lost it...

  • Member since
    May 2003
  • From: US
  • 25,276 posts
Posted by BaltACD on Thursday, January 27, 2022 8:04 PM

Not a MofW expert!

Looks very inefficient for what they are attempting to accomplish.

Never too old to have a happy childhood!

              

  • Member since
    December 2007
  • From: Georgia USA SW of Atlanta
  • 11,919 posts
Track construction and replacement around the world
Posted by blue streak 1 on Thursday, January 27, 2022 5:43 PM

Came across this rail replacement procedure apparently in Russia.  Very interesting use of track panels.  Old rail is sectioned into track panels and removed for apparently use elsewhere?  New panels installed but not joined.  Panel rail removed and long strips of welded rail installed.  Joining of long section thermited welded but joint bars installed as well.  Not trusting the Thermite  maybe because of temperature swings?  

MC  Any experience of this type replacement?

NOTE:  run the time back to beginning as link starts at 3:50

Капитальный ремонт железной дороги - все процессы / Railway track complete repair - all processes - YouTube

Join our Community!

Our community is FREE to join. To participate you must either login or register for an account.

Search the Community

Newsletter Sign-Up

By signing up you may also receive occasional reader surveys and special offers from Trains magazine.Please view our privacy policy