Trains.com

Pikes Peak Railroad rebuilding

3610 views
7 replies
1 rating 2 rating 3 rating 4 rating 5 rating
  • Member since
    September 2003
  • 21,325 posts
Pikes Peak Railroad rebuilding
Posted by Overmod on Thursday, May 21, 2020 4:02 PM

I can't believe no one has commented on this up to now, as I seem to remember quite a bit of wailing when the old railroad was closed (and rumored not to reopen with new-management priorities).

https://www.rtands.com/rail-news/railroad-construction-crews-attack-pikes-peak/

It'll be interesting to see what was learned in the course of this effort.

One unfortunate thing, though: it appears the rack system is being changed.  I have not heard anything about 'historic' steam power being modified (perhaps RyPN can weigh in with specific knowledge) and I doubt that even with 'biodiesel' or renewable-fuel firing there will be new steam to match the new railroad.

 

  • Member since
    May 2005
  • From: S.E. South Dakota
  • 13,567 posts
Posted by Murphy Siding on Thursday, May 21, 2020 4:54 PM

    $100 million for 8.9 miles of tourist rail that serves 2300 people a day during tourist season? How does that work? It's not real clear who is putting up the money.

Thanks to Chris / CopCarSS for my avatar.

  • Member since
    May 2003
  • From: US
  • 24,931 posts
Posted by BaltACD on Thursday, May 21, 2020 6:28 PM

Murphy Siding
    $100 million for 8.9 miles of tourist rail that serves 2300 people a day during tourist season? How does that work? It's not real clear who is putting up the money.

Of course the Broadmoor Hotel isn't politically connected Oops - Sign

Never too old to have a happy childhood!

              

  • Member since
    December 2007
  • From: Greendale, WI
  • 52 posts
Posted by saguaro on Wednesday, May 27, 2020 5:40 PM

Murphy Siding

    $100 million for 8.9 miles of tourist rail that serves 2300 people a day during tourist season? How does that work? It's not real clear who is putting up the money.

This is a major attraction in a state with a lot of major attractions. Let's say the tourist season is 90 days. Times 2,300 peer day -- that's 207,000 people in a year. They were all paying at least $35 each for the trip about five years ago when we went. That's over $7 million per year. That's not including souvenirs, food and lodging in the town that hosts the RR. Seems like a reasonable investment to me. For the RR, the town and the state.

 

  • Member since
    June 2003
  • From: South Central,Ks
  • 7,159 posts
Posted by samfp1943 on Thursday, June 11, 2020 10:18 PM

The following linked site is to a BLOG Posting with photos, from the Manitou area, and is detailing the rebuilding of the  125 year old Manitou & Pikes Peak line.  Locally, apparently, known as 'The COG' . 

  The blog post lays out in detail the several years process for the reconstruction of the line/ its center cog track, and the enlarging of the station at the bottom of the line; as well as the trains needed to service the line.    

   The costs [$100M] seems become more reasonable when it includs the total rebuild of the track and rack system, the lower station and the eight trains that service the line. Whistling 

 Linked @ https://www.pikes-peak.com/pikes-peak-cog-railway-closed/

 

 


 

  • Member since
    December 2007
  • From: Georgia USA SW of Atlanta
  • 11,824 posts
Posted by blue streak 1 on Monday, April 5, 2021 12:50 PM

The Pikes Peak is now open for buying tickets.  They are steep in price.  First trips start on thrusday May 27th.

The Broadmoor Manitou & Pikes Peak Cog Railway | Reopening in May 2021

  • Member since
    December 2001
  • From: Denver / La Junta
  • 10,785 posts
Posted by mudchicken on Monday, April 5, 2021 11:12 PM

(several of the older pieces of equipment now call CRRM-Golden home, including 1890 #1 (John Hulbert))

Several people, including Horace Sumner came off the M&PP and went directly to work on the DNW&P (Moffat Line).... 

Mudchicken Nothing is worth taking the risk of losing a life over. Come home tonight in the same condition that you left home this morning in. Safety begins with ME.... cinscocom-west
  • Member since
    June 2003
  • From: South Central,Ks
  • 7,159 posts
Posted by samfp1943 on Sunday, April 11, 2021 8:25 PM

mudchicken

(several of the older pieces of equipment now call CRRM-Golden home, including 1890 #1 (John Hulbert))

Several people, including Horace Sumner came off the M&PP and went directly to work on the DNW&P (Moffat Line).... 

 

 The $100 Million, when you add up what the wnershi of the M&PP RR is getting seems to be 'reasonable'(?) Sigh
 
The rack and rails were taken out, and the ROW was re-worked from the 'base' up.  The upper terminal/restaurant, and the lower station, were subject to 'rebuilding'.  (?)
 
New Trains, power and cars were ordered from Stadler, and a new Zaugg Snowblower was built in Switzerland. The rack system was replaced, as the old system was not compatible with the new Stadler equipment.
 
TRAINS has had at least one NEWSwire article, and a FORUM thread on the goings-on at the M&PP RR  
 
 

 

 


 

Join our Community!

Our community is FREE to join. To participate you must either login or register for an account.

Search the Community

Newsletter Sign-Up

By signing up you may also receive occasional reader surveys and special offers from Trains magazine.Please view our privacy policy