MR Express - Biggest challenges in tracklaying

15955 views
76 replies
1 rating 2 rating 3 rating 4 rating 5 rating
  • Member since
    December 2002
  • From: US
  • 736 posts
Posted by tomwatkins on Monday, August 18, 2003 6:59 PM
Getting powered switch machines adjusted so that they work reliably. Which of course means to throw completely every time. I decided to go with twin-pole machines instead of switch motors because of cost. Bad Decision. I'm currently converting as many turnouts as possible to manual operation.
  • Member since
    May 2003
  • From: CA
  • 170 posts
Posted by cp1057 on Sunday, August 10, 2003 10:17 PM
Tracklaying, eh? I'm having some trouble fitting turnouts into the trackplan. I lost about 18 inches of my staging tracks because I miscalculated the distance required for the tracks coming out of my turnout to diverge to the necessary spacing. It doesn't help that this is all happening on a curve.

I tried the idea from the August MR using adhesive caulk to lay flextrack. Works great!

I'm having some trouble with a turnout and switch machine, I've posted a description elsewhere in the forum.

Charles
Hillsburgh On
  • Member since
    May 2003
  • From: CA
  • 170 posts
Posted by cp1057 on Sunday, August 10, 2003 10:17 PM
Tracklaying, eh? I'm having some trouble fitting turnouts into the trackplan. I lost about 18 inches of my staging tracks because I miscalculated the distance required for the tracks coming out of my turnout to diverge to the necessary spacing. It doesn't help that this is all happening on a curve.

I tried the idea from the August MR using adhesive caulk to lay flextrack. Works great!

I'm having some trouble with a turnout and switch machine, I've posted a description elsewhere in the forum.

Charles
Hillsburgh On
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Sunday, August 10, 2003 2:54 AM
finding a satisfying track plan that i can fit in a 65 sq ft "L" shape in N scale..it took me months of work on atlas's ritetrack program...so far my plan is fitting....but its far from done....plenty of room for murphy to show up yet..im hoping that taking my time and test fitting with track pieces will avoid most of the aggravation ...plus i just look silly with red ears....scott
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Sunday, August 10, 2003 2:54 AM
finding a satisfying track plan that i can fit in a 65 sq ft "L" shape in N scale..it took me months of work on atlas's ritetrack program...so far my plan is fitting....but its far from done....plenty of room for murphy to show up yet..im hoping that taking my time and test fitting with track pieces will avoid most of the aggravation ...plus i just look silly with red ears....scott
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Thursday, August 7, 2003 4:41 PM
I'm with Avondale gy and Glen on this one.Getting N scale undermount turnout switches to work well and work everytime with enough constant pressure.
I wonder if Delaires setup is better than the rest?Other than that i lay track with diluted yellow glue and that works well for me.Also,I agree with Rick, Trackplans lie,not perhaps a baldfaced lie, just a little white one that turns into red heat coming out your ears!! [:D]
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Thursday, August 7, 2003 4:41 PM
I'm with Avondale gy and Glen on this one.Getting N scale undermount turnout switches to work well and work everytime with enough constant pressure.
I wonder if Delaires setup is better than the rest?Other than that i lay track with diluted yellow glue and that works well for me.Also,I agree with Rick, Trackplans lie,not perhaps a baldfaced lie, just a little white one that turns into red heat coming out your ears!! [:D]
  • Member since
    June 2003
  • From: Culpeper, Va
  • 8,204 posts
Posted by IRONROOSTER on Sunday, August 3, 2003 9:21 AM
Probably, doing spiral easements. I wrote a basic program to produce a table of measurements and then made a template from poster board. Worked really well.
enjoy
Paul
If you're having fun, you're doing it the right way.
  • Member since
    June 2003
  • From: Culpeper, Va
  • 8,204 posts
Posted by IRONROOSTER on Sunday, August 3, 2003 9:21 AM
Probably, doing spiral easements. I wrote a basic program to produce a table of measurements and then made a template from poster board. Worked really well.
enjoy
Paul
If you're having fun, you're doing it the right way.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Saturday, August 2, 2003 1:38 PM
The biggest challenge for me in tracklaying is just getting the track down smoothly. I work in N, and any little bump can wreck havoc on those tiny little wheels.

John
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Saturday, August 2, 2003 1:38 PM
The biggest challenge for me in tracklaying is just getting the track down smoothly. I work in N, and any little bump can wreck havoc on those tiny little wheels.

John
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Saturday, August 2, 2003 6:42 AM
Wow! After reading the other replies, I feel somewhat daunted. I've never considered handlaying my own track, mainly because I don't feel I have the patience for it. However, that may be a lame excuse. I find the hardest thing for me is to actually make the plans. Once I get them down on graph paper, I can do much better. The only decisions then are which turnouts to use, #4, #5, or #6 for the yards. I've downloaded the pages from the NMRA standards for the turnouts, so I have a guide. Now it's just a matter of transferring my ideas to paper and then to the actual layout.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Saturday, August 2, 2003 6:42 AM
Wow! After reading the other replies, I feel somewhat daunted. I've never considered handlaying my own track, mainly because I don't feel I have the patience for it. However, that may be a lame excuse. I find the hardest thing for me is to actually make the plans. Once I get them down on graph paper, I can do much better. The only decisions then are which turnouts to use, #4, #5, or #6 for the yards. I've downloaded the pages from the NMRA standards for the turnouts, so I have a guide. Now it's just a matter of transferring my ideas to paper and then to the actual layout.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Friday, August 1, 2003 12:06 PM
i find that keeping the rails together is very difficult
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Friday, August 1, 2003 12:06 PM
i find that keeping the rails together is very difficult
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Thursday, July 31, 2003 4:00 PM
Getting smooth, kink-free joints on curves when using Peco Code 55. Those rails don't slide though the ties very easily, so all the good advice about staggering the joints is useless.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Thursday, July 31, 2003 4:00 PM
Getting smooth, kink-free joints on curves when using Peco Code 55. Those rails don't slide though the ties very easily, so all the good advice about staggering the joints is useless.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Wednesday, July 30, 2003 5:38 PM
My biggest challenge is getting the N scale Peco manual turnout linkage to work the undertable microswitches. With too many switches the turnout throwbar spring can no longer hold against the microswitch pressure. Have tried different methods with varying degrees of success.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Wednesday, July 30, 2003 5:38 PM
My biggest challenge is getting the N scale Peco manual turnout linkage to work the undertable microswitches. With too many switches the turnout throwbar spring can no longer hold against the microswitch pressure. Have tried different methods with varying degrees of success.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Tuesday, July 29, 2003 11:50 PM
The biggest challenge for me is to get the technical aspect of how tracks and yards in general should work, then move the theoretical to the practical. I have made at least a hundred track plans in my mind for the space I have available, and what I am laying now only mildly resembles what went on in my brain. So I think the greatest difficulty is getting the experience so that a reasonable track plan can be had that reflects my givens and druthers.

Curves eat more than I realized. Trying to be true to a minimum mainline curve can be tricky and demanding.

So I guess for me the most demanding aspect of track laying is getting the experience.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Tuesday, July 29, 2003 11:50 PM
The biggest challenge for me is to get the technical aspect of how tracks and yards in general should work, then move the theoretical to the practical. I have made at least a hundred track plans in my mind for the space I have available, and what I am laying now only mildly resembles what went on in my brain. So I think the greatest difficulty is getting the experience so that a reasonable track plan can be had that reflects my givens and druthers.

Curves eat more than I realized. Trying to be true to a minimum mainline curve can be tricky and demanding.

So I guess for me the most demanding aspect of track laying is getting the experience.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Tuesday, July 29, 2003 6:02 PM
I have trouble with the switch operating mechanisms. I work in N-scale, and I had planned to use a mechanical manual throw for all my switches (motors are just more things that can break down over time), but the product I tried was based on a bent piano wire spring to hold the points in place. The problem is that the piano wire, which is intended to poke through the tie rod for its connection, is too wide; it is as wide as my N-scale tie rod. So that means that I have to find another way to connect it, and CA glue did not hold up over time (I'm back to pushing them loose with my finger). Soldering is a bad idea because 1. I cannot solder (I know this, I accept it) and 2. The points are already soldered to the tie rod and will loosen & shift. Aaargh! There has to be a way.
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Tuesday, July 29, 2003 6:02 PM
I have trouble with the switch operating mechanisms. I work in N-scale, and I had planned to use a mechanical manual throw for all my switches (motors are just more things that can break down over time), but the product I tried was based on a bent piano wire spring to hold the points in place. The problem is that the piano wire, which is intended to poke through the tie rod for its connection, is too wide; it is as wide as my N-scale tie rod. So that means that I have to find another way to connect it, and CA glue did not hold up over time (I'm back to pushing them loose with my finger). Soldering is a bad idea because 1. I cannot solder (I know this, I accept it) and 2. The points are already soldered to the tie rod and will loosen & shift. Aaargh! There has to be a way.
  • Member since
    March 2002
  • From: US
  • 5 posts
Posted by mikemc on Monday, July 28, 2003 11:03 AM
I had been using adhesive caulk to attach Homasote and Homa-Bed to my subroadbed. I recall reading this tip in MR many years ago. But I never thought about using it for track. I didn't think it would hold too well for curved flex track but it does!

I use Atlas code 83 flex and Walthers code 83 turnouts. The ties on the Atlas track are thicker than the Walthers, so I cut square pieces of styrene and glue them to the turnout ties. I then apply the adhesive to these small styrene pieces and situate the turnout, instead of covering the whole area.

A challenge I have had was the stock rails on the Walthers turnouts coming out of their spikes. This has caused guage problems and derailment issues. Not on every turnout, just a few, But it is hard to fix, I am still working on a curved #7 turnout that causes shorts and derailments because of this. I'd rather not replace it at $25 for the turnout.

Mike Mc.
  • Member since
    March 2002
  • From: US
  • 5 posts
Posted by mikemc on Monday, July 28, 2003 11:03 AM
I had been using adhesive caulk to attach Homasote and Homa-Bed to my subroadbed. I recall reading this tip in MR many years ago. But I never thought about using it for track. I didn't think it would hold too well for curved flex track but it does!

I use Atlas code 83 flex and Walthers code 83 turnouts. The ties on the Atlas track are thicker than the Walthers, so I cut square pieces of styrene and glue them to the turnout ties. I then apply the adhesive to these small styrene pieces and situate the turnout, instead of covering the whole area.

A challenge I have had was the stock rails on the Walthers turnouts coming out of their spikes. This has caused guage problems and derailment issues. Not on every turnout, just a few, But it is hard to fix, I am still working on a curved #7 turnout that causes shorts and derailments because of this. I'd rather not replace it at $25 for the turnout.

Mike Mc.
  • Member since
    March 2002
  • From: Milwaukee WI (Fox Point)
  • 11,439 posts
Posted by dknelson on Monday, July 28, 2003 8:24 AM
The biggest challenge in tracklaying is getting off my *#^%&%( butt and get to work.

The second biggest challenge is to realize that track plans lie -- especially the ones you create. In fact they lie the worst of all.

Dave Nelson
  • Member since
    March 2002
  • From: Milwaukee WI (Fox Point)
  • 11,439 posts
Posted by dknelson on Monday, July 28, 2003 8:24 AM
The biggest challenge in tracklaying is getting off my *#^%&%( butt and get to work.

The second biggest challenge is to realize that track plans lie -- especially the ones you create. In fact they lie the worst of all.

Dave Nelson
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Friday, July 25, 2003 11:45 PM
Well, laying track has never been too difficult for me, although it HAS been several years.

I was laying Atlas flextrack and switches.

The worst party was trying to paint the rails later with a brush... I was kind of sloppy. Next time - airbrush.

I've tried handlaying track. Regular track wasn't too much of a problem - turnouts have defeated me.

I tried building in place - actually finished one - but it didn't work well enough to keep. I tried building one at the bench - per Tony Koester's article - I didn't finish it.

I would love to handlay all my track - turnouts (and crossings) are what scare me away. On my next railroad (hopefully to be started later this year) I will be using Micro-Engineering or Walthers Flextrack, and Walthers/Shinohara turnouts. I may go back - one turnout at a time, and replace them with hand-built.

So... Biggest challenge is handlaying turnouts - I will overcome it by buying pre-made :D

Rob
  • Member since
    April 2003
  • 305,205 posts
Posted by Anonymous on Friday, July 25, 2003 11:45 PM
Well, laying track has never been too difficult for me, although it HAS been several years.

I was laying Atlas flextrack and switches.

The worst party was trying to paint the rails later with a brush... I was kind of sloppy. Next time - airbrush.

I've tried handlaying track. Regular track wasn't too much of a problem - turnouts have defeated me.

I tried building in place - actually finished one - but it didn't work well enough to keep. I tried building one at the bench - per Tony Koester's article - I didn't finish it.

I would love to handlay all my track - turnouts (and crossings) are what scare me away. On my next railroad (hopefully to be started later this year) I will be using Micro-Engineering or Walthers Flextrack, and Walthers/Shinohara turnouts. I may go back - one turnout at a time, and replace them with hand-built.

So... Biggest challenge is handlaying turnouts - I will overcome it by buying pre-made :D

Rob
  • Member since
    November 2002
  • From: Texas, USA
  • 120 posts
Posted by ssgauge on Friday, July 25, 2003 6:57 PM
I handlay my own track and use "hot frogs" in my switches...I like the smooth operation through the frog, especially with solder-based flangeways. I also like to have a prototypical gap between the open point rail and the stock rail, but that of course can lead to electrical shorts when the back of the locomotive driver comes close to or even lightly touches the open point rail. The solution was to paint the back (inside of the locomotive drivers and tender wheels. I used dark brown Floquil water-based paint and it effectively insulates the inside face of the driver and eliminates the shorts.

Subscriber & Member Login

Login, or register today to interact in our online community, comment on articles, receive our newsletter, manage your account online and more!

Users Online

There are no community member online